Wind turbines shut down amid investigation into collapse
Credit: 'The blade is wrapped around the bottom of it and the engine is on the ground' | CBC News | Posted: Jan 22, 2018 | www.cbc.ca ~~
Translate: FROM English | TO English
Translate: FROM English | TO English
A company in Chatham-Kent, Ont. has shut down all 51 of its wind turbines as a precaution until an investigation reveals what caused one of the turbines to collapse last Friday.
The turbine in Raleigh Township, near the corner of Drake Road and the 16th Line, collapsed on itself.
Representatives from the company which owns the turbine, TerraForm Power, were at the site Monday inspecting the damage. The area has been blocked off with temporary plastic fencing.
“It’s a warning to me,” said Chatham-Kent Ward 2 Coun. Frank Vercouteren. “I’ve noticed that some of these turbines are pretty close to the road. That distance has to be more.”
Under investigation
Director of investor relations for TerraForm power, Chad Reed, told CBC News in an emailed statement that the cause is being investigated by a “team of experts.”
“We are making progress on the inspection and expect to complete it within the coming weeks. As a precaution, the facility will remain offline until the inspection is complete.”
The Ministry of Labour and the Ministry of the Environment and Climate Change are also investigating.
In an emailed statement to CBC News, a spokesperson for the Ministry of Labour said that an inspector and engineer attended the scene and issued no orders or requirements.
Ministry of Environment spokesperson Gary Wheeler said in an emailed statement to CBC News that his ministry is taking the incident “very seriously” and “will ensure that the company determines the cause of the incident.”
Reed said his company will provide more details on which company built the tower portion of the turbine once the investigation is complete.
CBC News is trying to determine whether CS Wind manufactured the tower components. The company has not responded to calls.
The turbine was originally constructed by Graham Construction of Calgary in 2009. It was owned by Raleigh Wind Power which brought the turbine online in January of 2011. TerraForm purchased Raleigh Wind Power in 2015.
This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.
Wind Watch relies entirely on User Contributions |
(via Stripe) |
(via Paypal) |
Share:
Tag: Accidents |