A group fighting a controversial wind farm development south of Picton, Ont., says its final appeal will be heard in December.
The Prince Edward County Field Naturalists says it has been told that the Court of Appeal for Ontario will hear the case in Toronto on Dec. 8 and 9.
The group will explain why it is opposed to Gilead Power’s plans for a nine-turbine facility at Ostrander along the north shore of Lake Ontario.
The activists believe it is the wrong place for a wind farm for a number of reasons, including the area’s importance to migrating birds, bats and butterflies.
The group was granted permission earlier this summer to appeal an Ontario Divisional Court ruling.
That ruling agreed with the developer and the Environment Ministry’s appeal of an Environmental Review Tribunal finding that the project should not proceed.
This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this article resides with the author or publisher indicated. As part of its noncommercial effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.
Wind Watch relies entirely on User Funding |
![]() |
![]() |
Share: