Ashtabula wind farm first in ND to re-power
Credit: By Dave Thompson | Prairie Public | prairiepublic.org ~~
A wind farm in Barnes County is the first facility in North Dakota to be re-powered – that is, upgraded from the original.
The Public Service Commission has okayed the re-power plan. Under it, Ashtabula Wind will replace existing turbines with newer, more power-generating models, that will increase its capacity from 148.5 megawatts to 160.4 megawatts. The turbine blades will also be larger.
The company had started work on the site before the PSC acted.
“It doesn’t meet the definition of construction under the law,” said Commissioner Julie Fedorchak. “This type of construction is an upgrade, and the ‘footprint law’ allows companies to make upgrades, improvements, put in new facilities, etc. in the previously approved area without receiving approval from the Commission. That’s what this is.”
Fedorchak said the Commission’s order removes any reference to a “nameplate” generation capacity. She said that might make it a little easier for the company to repower again. But Fedorchak said the company will still have to abide by PSC rules on noise and shadow-flicker.
This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.
Wind Watch relies entirely on User Contributions |
![]() (via Stripe) |
![]() (via Paypal) |
Share: