Supreme Court date set for Trump windfarm case
Credit: By Lindsay Watling | The Press and Journal | 25 September 2015 | www.pressandjournal.co.uk ~~
Translate: FROM English | TO English
Translate: FROM English | TO English
Donald Trump will take his fight against plans for an offshore windfarm near his north-east golf resort to the highest court in the land next month.
The tycoon’s case will be heard at the UK Supreme Court in central London on October 8.
The Court of Session rejected Mr Trump’s appeal against the £230million European Offshore Wind Deployment Centre (EOWDC).
His bid for a judicial review of the Scottish Government’s decision to allow the 11-turbine development in Aberdeen Bay – on the grounds it was unlawful – was first dismissed in February last year.
New York-based Mr Trump, who believes the scheme will spoil the views from Trump International Golf Links, Scotland near Balmedie in Aberdeenshire, then lodged an appeal against the ruling, but it was also rejected in June.
He had claimed the scheme’s approval was predetermined and the Scottish Government showed a bias in favour of the development.
But the judgment concluded “none of the considerations founded on by the petitioners comes anywhere near to supporting the petitioners’ suspicions”.
Former first minister Alex Salmond later urged the businessman to accept the decision, given the need to create jobs in renewables in light of the difficulties being faced by the oil and gas industry.
But the Republican US presidential hopeful vowed to take the case all the way to Europe if necessary.
It was “impossible” to have a fair hearing challenging windfarm applications in Scotland, the Trump Organisation claimed.
The Supreme Court hearing, which is due to last a day, will examine how the Electricity Act 1989 should be interpreted in terms of a party’s eligibility to apply for consent to construct a generating station.
It will consider whether the planning consent, granted by Scottish ministers in 2013, was so imprecise as to impair its legal validity.
Judges will also look at whether one of the conditions of the consent is void in the absence of an enforcement mechanism for ensuring compliance with the windfarm’s design statement.
The case will be heard by justices Lord Neuberger, Lord Mance, Lord Reed, Lord Carnwath and Lord Hodge.
A spokesman for Aberdeen Offshore Wind Farm Ltd, the company behind the centre, said the partners – AREG and Vattenfall – hoped for a “speedy resolution”.
He added: “Both partners want to see the scheme come to fruition as it would benefit the energy economy of the north-east of Scotland and help the Scottish consumer by promoting reductions in the cost of generation from offshore wind.”
The Trump Organisation said it would not comment until after the final judgment.
This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.
Wind Watch relies entirely on User Contributions |
(via Stripe) |
(via Paypal) |
Share: