LOCATION/TYPE

NEWS HOME

[ exact phrase in "" • results by date ]

[ Google-powered • results by relevance ]



Archive
RSS

Add NWW headlines to your site (click here)

Get weekly updates

WHAT TO DO
when your community is targeted

RSS

RSS feeds and more

Keep Wind Watch online and independent!

Donate via Stripe

Donate via Paypal

Selected Documents

All Documents

Research Links

Alerts

Press Releases

FAQs

Campaign Material

Photos & Graphics

Videos

Allied Groups

Wind Watch is a registered educational charity, founded in 2005.

News Watch Home

Lee County settles with couple over wind farm 

Credit:  BY DAVID GIULIANI | Jan 13, 2014 | www.saukvalley.com ~~

DIXON – Lee County residents Margina and Larry Schwartzbach say the county failed to notify them of a wind farm going up in their neighborhood.

The county never denied it.

In September, the county settled a lawsuit filed by the Schwartzbachs, giving the couple $5,000.

According to online court records, the Schwartzbachs also settled with Goldwind USA, the wind farm’s owner, and Mainstream Renewable Power, the previous owner.

The Shady Oaks wind project started operating in June 2012 in southern Lee County, near the villages of Compton and West Brooklyn. Goldwind is the subsidiary of a Chinese company.

Under open government laws, the county could not keep the settlement amount secret. Private companies have no such requirement.

Matt Klahn, a Lee County assistant state’s attorney, said the county gives wind farm companies the addresses of those who must receive notices about proposed projects, while the firms mailing them out.

With the Goldwind wind farm, four permits were involved, so the process became complicated, Klahn said.

As for the lack of notice, he said, it was an “honest mistake.”

“There were multiple people who missed it. You can’t pin this on one person,” Klahn said. “We appreciated working with the Schwartzbachs. They are nice people.”

The county’s insurance carrier covered the attorney’s fees and mediation costs, Klahn said. Because of the deductible, he said, the $5,000 was paid out of the county’s general fund.

In 2012, Margina Schwartzbach spoke during a county zoning board meeting, at which the panel was considering another wind farm. She said Goldwind project had disrupted their lives.

A turbine near her house, she said, was a constant bother.

“It’s very annoying,” she told the board. “It produces loud humming sounds.”

At night, she said, it was unbearable.

“We turn on the TV to drown it out, so we can fall asleep,” Schwartzbach said. “We don’t hear the crickets at night or birds in the morning.”

The Schwartzbachs said they found out about the wind farm when construction started in October 2011. The one turbine is 1,400 feet to the west of their home, the minimum distance the county allows.

Last year, Sauk Valley Media filed a public records request for any documents that showed the couple had received notice about the wind farm petition. The county produced nothing.

In their lawsuit, the Schwartzbachs asked the court to decommission the offending turbines and to award them damages of more than $50,000.

They filed the lawsuit without a lawyer, but by the end, they were represented by Rodney Kimes, a Beloit attorney. Neither Kimes nor the Schwartzbachs could be reached for comment.

No new wind farms in Sauk Valley

Last May, the Lee County Board approved a controversial wind farm, involving 53 turbines in the far southwestern part of the county.

The previous year, Whiteside County signed off on nine turbines for the same project, owned by Ireland-based Mainstream Renewable Power.

Not one turbine has gone up yet.

About all that’s happened is litigation. Residents near the proposed wind farm have filed a yet-to-be-resolved lawsuit against the project.

Stuart Richter, Whiteside County’s zoning administrator, figured that the litigation has stalled the Mainstream project.

A manager with Mainstream couldn’t be reached for comment Friday.

In general, area counties are not seeing any interest in new wind farms, a change from previous years.

Lee County, which got the state’s first wind farm a decade ago, knows of no companies considering projects.

“We’re probably maxed out, as far as placement of turbines, because of the saturation we have,” said Chris Henkel, Lee County’s zoning administrator. “We have 230-plus turbines. We’re pretty full.”

Officials in Whiteside, Bureau and Ogle counties also say they have no new applicants for wind farms.

Part of the reason, officials say, is the uncertainty over production tax credits for wind farms, which has spurred development over the years.

Source:  BY DAVID GIULIANI | Jan 13, 2014 | www.saukvalley.com

This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.

The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.

Wind Watch relies entirely
on User Funding
   Donate via Stripe
(via Stripe)
Donate via Paypal
(via Paypal)

Share:

e-mail X FB LI M TG TS G Share

Tag: Complaints


News Watch Home

Get the Facts
CONTACT DONATE PRIVACY ABOUT SEARCH
© National Wind Watch, Inc.
Use of copyrighted material adheres to Fair Use.
"Wind Watch" is a registered trademark.

 Follow:

Wind Watch on X Wind Watch on Facebook Wind Watch on Linked In

Wind Watch on Mastodon Wind Watch on Truth Social

Wind Watch on Gab Wind Watch on Bluesky