LOCATION/TYPE

NEWS HOME



[ exact phrase in "" • results by date ]

[ Google-powered • results by relevance ]

Archive
RSS

Add NWW headlines to your site (click here)

WHAT TO DO
when your community is targeted

Get weekly updates
RSS

RSS feeds and more

Keep Wind Watch online and independent!

Donate via Stripe

Donate via Paypal

Selected Documents

All Documents

Research Links

Alerts

Press Releases

FAQs

Campaign Material

Photos & Graphics

Videos

Allied Groups

Wind Watch is a registered educational charity, founded in 2005.

News Watch Home

CapX 2020 transmission project enters final stretch 

Credit:  by Frank Jossi | Midwest Energy News | www.midwestenergynews.com 17 July 2012 ~~

After years of planning, debate, and regulatory procedures, one of the largest transmission projects in the country is on track to be completed by 2015.

CapX2020 reached a major milestone in receiving an approval from Wisconsin officials in May, while igniting an ownership battle over a related line in the Badger State.

The Wisconsin Public Service Commission in May gave approval to the final CapX2020 leg, which crosses the Mississippi River at Alma, Wisconsin, before heading south toward LaCrosse. Prior to that, the Minnesota Public Utilities Commission approved the state’s final portion, from Hampton to Alma, in April.

Although landowners and individuals opposed to CapX have raised objections, the Wisconsin PSC denied all 14 petitions by a 3-0 vote last week. Minnesota’s PUC will soon hear two petitions against the project.
Tapping western wind power

The $2.2 billion spider web of 800 miles of high transmission power lines criss-cross four states before terminating in Wisconsin, where another utility plans to potentially continue it to Madison.

Tim Noeffler, vice president of special projects for the LaCrosse-based WPPI Energy, said initially the utility had planned to add two 161 kilovolt lines from Alma but decided instead to continue with same voltage, 345 kV, as the rest of the line.

The higher voltage increases the amount of power that can be transported, primarily from wind farms, to Wisconsin’s grid by 1,200 megawatts, the equivalent of a nuclear power plant. Much of Wisconsin’s wind power, at least in the southwest, already comes from wind farms in Minnesota, Iowa and the Dakotas.

“The renewable energy is cheaper to the west of Wisconsin because there’s a higher constant average wind speed than you can get in Wisconsin,” he said. “The wind capacity in Wisconsin is 30 percent while in North Dakota and southern Minnesota it’s closer to 45 percent.”

The ability to buy more renewables will not only affect WPPI but other utilities looking to meet the state’s renewable portfolio standard or who may need to prepare for carbon pricing at some point in the future, said Noeffler.
Ownership dispute

CapX’s end point has raised a tussle between companies in Minnesota and Wisconsin. Tim Carlsgaard, Xcel Energy’s spokesman for CapX, said Xcel charges that Waukesha-based American Transmission Co. must share ownership of its proposed Badger Coulee line from LaCrosse to Madison.

The Federal Energy Regulatory Commission (FERC) rules require a utility that is asking to access the power from another utility’s substation offer a joint ownership arrangement of any proposed lines. ATC argues it can own the line while using the Xcel Energy Briggs Road Substation near Homan as a link to the electrical grid.

Xcel argues that federal and regulations give it co-ownership. “We have that ownership right and we don’t want to give it up,” Carlsgaard said.

The Midwest Independent System Operator (MISO) designated the Badger Coulee as a “multi-value project” and approved it with ownership being shared by Xcel and ATC, he added.

FERC will decide the ownership outcome. “We fully expect the FERC will rule in our favor,” said Anne Spaltholz, ATC’s corporate communications manager. The utility has studied the 150 to 170 mile long line, expected to cost $425 million, for several years, she said, with little input from Xcel.
Elsewhere

In another recent CapX development the $490 million Brookings to Hampton section received state approval in Minnesota after the PUC rejected the recommendations made by an administrative law judge to change the route.

The more than 150 mile stretch includes a connection to two 161kV lines to Rochester that branch off the 345 kV line. The 2 substations that those lines will connect to are owned by Rochester Public Utilities.

For Rochester the line adds reliability to a rapidly growing region. The prospect of a biotech campus emerging in Pine Island may increase, too, the need for more electricity, Carlsgaard said.

The other projects are in various stages of completion. Here’s a rundown.

Bemidji to Grand Rapids, Minnesota: Being built in three phases, the 70 mile line’s first half, from Grand Rapids to Cass Lake, will be completed this month and begin transmitting power. The Cass Lake to Bemidji section will be completed in September and the rest by December.

Brookings County, South Dakota, to Hampton, Minnesota: The longest stretch of CapX2020, at 250 miles, is under construction. The building of foundations for towers carrying 345 kV lines began in May in Renville County. The crews will head east first, and then work west. The line will be completed in 2015.

Fargo, North Dakota-St. Cloud, Minnesota: A 30-mile portion of this 210 mile, 345 kV between Monticello, Minnesota and St. Cloud went live in December 2011. Foundations are being built now between St. Cloud and Alexandria and the towers will go in this fall. Foundation works starts from Alexandra to the border this fall. The North Dakota Public Service Commission votes this summer to approve the line.

Hampton, Minnesota-Rochester-LaCrosse: The 180 mile project (a total including the two Rochester lines) will have 345kV lines crossing Minnesota before heading across the Mississippi. The final line needs one more approval, from the Rural Utilities Service Commission. Work will begin January 2013.

Big Stone to Brookings, South Dakota: A recent addition to the project, the 70 mile line received approval from MISO as a multi-value project, or MVP. The 345 kV project will run from a large coal-fired plant in Big Stone to Brookings County on a path near the Minnesota border.

“There may be a bigger transmission build out in the country but I don’t know of it,” said Carlsgaard. “For us CapX is about local reliability and being able to add more renewables. Those are the biggest positives that will come out of these projects.”

Source:  by Frank Jossi | Midwest Energy News | www.midwestenergynews.com 17 July 2012

This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.

The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.

Wind Watch relies entirely
on User Contributions
   Donate via Stripe
(via Stripe)
Donate via Paypal
(via Paypal)

Share:

e-mail X FB LI M TG TS G Share


News Watch Home

Get the Facts
CONTACT DONATE PRIVACY ABOUT SEARCH
© National Wind Watch, Inc.
Use of copyrighted material adheres to Fair Use.
"Wind Watch" is a registered trademark.

 Follow:

Wind Watch on X Wind Watch on Facebook Wind Watch on Linked In

Wind Watch on Mastodon Wind Watch on Truth Social

Wind Watch on Gab Wind Watch on Bluesky