Kahuku wind farm idled during work on battery system
Credit: By Star-Advertiser Staff, www.staradvertiser.com 7 June 2011 ~~
Translate: FROM English | TO English
Translate: FROM English | TO English
First Wind LLC said it has temporarily idled the turbines at its Kahuku wind energy project while it works on the battery storage system.
The 12 wind turbines were shut down on May 22 and are expected to be brought back online in stages starting later this week, company spokesman John Lamontagne said in an email from the company’s headquarters in Massachusetts.
“We are conducting a diligent and thorough review of the operating issues for the battery facility at the Kahuku project. During that time, the project is offline,” he said.
The 30-megawatt project – Oahu’s only commercial-scale wind farm – began feeding electricity into Hawaiian Electric Co.’s grid in March. The turbines produce enough energy to power about 7,700 homes, according to First Wind. First Wind sells the electricity to HECO at a fixed price of 19.9 cents per kilowatt-hour under a 20-year purchase power agreement.
This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.