Steuben County windmill project delayed
COHOCTON – The start of construction on the Cohocton Wind and Dutch Hill windmill projects in northern Steuben County will be delayed several days while a study of road conditions in the area is completed.
The study was required by Steuben County before it would allow the heavy construction trucks involved in the windmill project to use six county highways, said Vince Spagnoletti, public works commissioner.
“Six county roads have been identified that they are going to use to haul heavy loads to the windmill sites,” Spagnoletti said. “They have signed an agreement to do an engineering study that will show the existing condition of the roads before they put their heavy traffic on them.”
Canandaigua Power Partners II, the sponsor of the windmill project, has already signed a cost-sharing agreement to bring the roads back to their original condition after the windmill project is complete, Spagnoletti said.
“The study should take about two or three days,” Spagnoletti said. “It won’t lead to any long-term delay.”
The county posted a 10-ton weight limit on the roads involved to keep the heavy traffic off them until the engineering study is done, Spagnoletti said.
“It does not apply to local deliveries or farm tractors or milk trucks,” he said.
The county roads involved are County Route 35 in Cohocton, County Route 121 in Wayland and Cohocton, County Route 36 in Wayland and Cohocton, County Route 6 in Howard and Avoca, County Route 105 in Avoca and County Route 7 in Avoca, Wheeler and Prattsburg.
Construction had been scheduled to begin Monday on the Dutch Hill projects, which involves 16 wind turbines. The Cohocton Wind project will include 35 turbines. The two projects will occupy more than 7,000 acres of leased lands.
August 28, 2007
Star-Gazette
This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this article resides with the author or publisher indicated. As part of its noncommercial effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.
Wind Watch relies entirely on User Funding |
![]() |
![]() |
Share: