Third knock-back for wind scheme
Translate: FROM English | TO English
Translate: FROM English | TO English
A judge has backed a decision to refuse planning permission for a wind farm near the Dounreay nuclear plant.
Highland Council had rejected the scheme for 10 turbines at Borrowston Mains, in Caithness.
A reporter appointed by Scottish ministers also turned down an appeal by CRE Energy Ltd.
The company then took the case to the Court of Session in Edinburgh, but Lord Kinclaven ruled that he supported the reporter’s decision.
The judge said: “I was satisfied that his decision in relation to landscape and visual impacts was well founded.”
He added: “I was also satisfied that the adverse conclusion in relation to landscape and visual impacts was bound to lead to refusal of the appeal.”
Lord Kinclaven said that an error in a decision letter did not amount to a material misdirection.
Highland Council had maintained that the turbine development would represent a dominant feature in the landscape that was considered unacceptable.
This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.
Wind Watch relies entirely on User Contributions |
(via Stripe) |
(via Paypal) |
Share: