Cape Wind lease on New Bedford docks canceled
Credit: By Jack Newsham, Globe Correspondent | The Boston Globe | March 02, 2015 | www.bostonglobe.com ~~
Translate: FROM English | TO English
Translate: FROM English | TO English
Despite attempts by the developers of Cape Wind to save the project, another component of the planned offshore wind farm has fallen through.
The quasi-public Massachusetts Clean Energy Center said Monday that the agency and Cape Wind “mutually agreed” to end Cape Wind’s lease of 28 acres of heavy-duty waterfront industrial space in New Bedford. The $4.5 million lease was supposed to run through the end of 2016.
The lease termination comes several months after National Grid and Eversource Energy said they were pulling out of electricity purchase contracts because the renewable energy developer didn’t meet a January 1 financing deadline. The utilities were supposed to buy the vast majority of the electricity generated by the 130-turbine wind farm at an above-market rate.
“As part of a process that began in April 2014, MassCEC is seeking a professional terminal operator to manage and maximize economic activity at the facility,” said a spokeswoman for the Clean Energy Center. “This termination will provide clarity to the prospective operators regarding Cape Wind’s near-term use of the terminal.”
At a Saturday rally on the Boston Common, Cape Wind president Jim Gordon said his company was still negotiating with the utilities to salvage the development. He said “relentless litigation” by opponents of the project posed an unusual challenge and should be taken into consideration by the electric companies.
“We are not giving up,” Gordon said at the Saturday rally. “We have just begun to fight.”
The Globe reported in September that the state spent $100 million to dredge, engineer, and clean up New Bedford’s harbor with hopes that it would be used as a staging area for other offshore wind developments. Now, it’s unclear whether Cape Wind will ever return to the area, although MassCEC said it would be willing to renegotiate a lease if the developer were to resolve its financing issues.
This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.
Wind Watch relies entirely on User Funding |
(via Stripe) |
(via Paypal) |
Share: