Plans for power transmission route OK’d
Credit: Argus Leader, www.argusleader.com 8 February 2011 ~~
Translate: FROM English | TO English
Translate: FROM English | TO English
The Minnesota Public Utilities Commission has approved the final section of a transmission route that would ferry wind power from South Dakota to the Twin Cities.
The 250-mile transmission line from Brookings County to Hampton, Minn., just south of St. Paul, had been permitted except for a 60-mile stretch where it would cross the Minnesota River.
U.S. Fish and Wildlife Service had raised concerns about how the transmission line might affect eagles flying along the river corridor. The FWS since has withdrawn its letter of concern, a Minnesota PUC spokesman said.
The Brookings line is one of four new transmission lines proposed by CapX2020, a group of 11 utility companies working to upgrade the regional grid infrastructure at a cost of $1.7 billion. The South Dakota Public Utilities Commission approved the 10.6-mile section in South Dakota last month.
This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.
Wind Watch relies entirely on User Funding |
(via Stripe) |
(via Paypal) |
Share: