Decision on Bull Hill Wind expected Oct. 5
Credit: Written by Cyndi Wood, fenceviewer.com 27 September 2011 ~~
Translate: FROM English | TO English
Translate: FROM English | TO English
ELLSWORTH – The state Land Use Regulation Commission is expected to issue a decision on the Bull Hill Wind project Wednesday, Oct. 5, during a meeting at the Ramada Inn.
Blue Sky East, a subsidiary of wind developer First Wind, proposes to build a 19-turbine wind facility on the Bull Hill and Heifer Hill ridges in Township 16, which borders Eastbrook. The $78.5-million project would have a maximum capacity of about 34 megawatts. The turbines would be 476 feet high.
The Oct. 5 meeting will begin at 9:30 a.m. in the Ramada conference room.
In addition to the Bull Hill decision, the LURC commissioners are also scheduled to begin deliberations on the Bowers Wind Project proposed for Carroll Plantation in Penobscot County and Kossuth Township in Washington County.
Champlain Wind, also a First Wind subsidiary, submitted the permit application for the 69-megawatt project.
Information about both wind development proposals is available on the LURC website at www.maine.gov/doc/lurc/.
This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.
Wind Watch relies entirely on User Funding |
(via Stripe) |
(via Paypal) |
Share: