NYISO interconnection queue wind projects

As of April 8, 2009, seventy wind projects are in the New York Independent System Operator (NYISO) interconnection queue [click here for latest information from NYISO [1]], accounting for (summer) nameplate generation capacity of nearly 9,200 megawatts (1,400 of which result from the offshore LIPA project). Of these projects:

The projects in the queue, sorted by county location, are:

{Planned in-service [yr/mo]} Project & county (owner/developer) [Summer MW]

{I/S} Altona Windfield in Clinton, NY (Noble Environmental Power, LLC) [99]
{I/S} Bliss II Windfield in Wyoming, NY (Noble Environmental Power, LLC) [28.5]
{I/S} Bliss Windfield in Wyoming, NY (Noble Environmental Power, LLC) [72]
{I/S} Canandaigua II in Steuben, NY (UPC Wind Management, LLC) [42.5]
{I/S} Canandaigua Wind Farm in Steuben, NY (UPC Wind Management, LLC) [82.5]
{I/S} Chateaugay Windpark in Franklin-Clinton, NY (Noble Chateaugay Windpark, LLC) [106.5]
{I/S} Clinton II Windfield in Clinton, NY (Noble Environmental Power, LLC) [21]
{I/S} Clinton Windfield in Clinton, NY (Noble Environmental Power, LLC) [79.5]
{I/S} Ellenburg Windfield in Clinton, NY (Noble Environmental Power, LLC) [79.5]
{I/S} Flat Rock Wind Power in Lewis, NY (Flat Rock Wind Power, LLC) [321]
{I/S} Wethersfield 230kV in Wyoming, NY (Noble Wethersfield Windpark, LLC) [126]
{2009} Ellenburg II Windfield in Clinton, NY (Noble Environmental Power, LLC) [21]
{2009} Howard Wind in Steuben, NY (Howard Wind, LLC) [62.5]
{2009/02} High Sheldon Windfarm in Wyoming, NY (Sheldon Energy, LLC) [112.5]
{2009/02} Windhorse Beekmantown in Clinton, NY (Windhorse Power, LLC) [19.5]
{2009/10} Chateaugay II Windpark in Franklin, NY (Noble Chateaugay Windpark II, LLC) [19.5]
{2009/11} Dairy Hills Wind Farm in Wyoming, NY (Dairy Hills Wind Farm, LLC) [120]
{2009/11} Prattsburgh Wind Park in Yates, NY (Windfarm Prattsburgh, LLC) [55.5]
{2009/11} West Hill Windfarm in Madison, NY (NY Windpower, LLC) [37.5]
{2009/12} Allegany Windpark in Cattaraugus, NY (Noble Allegany Windpark, LLC) [100.5]
{2009/12} Ashford Wind in Cattaraugus, NY (Ashford Wind Farm, LLC) [19.9]
{2009/12} Canisteo Hills Windfarm in Steuben, NY (Invenergy NY, LLC) [148.5]
{2009/12} Dean Wind in Tioga – Schuyler, NY (Gamesa Energy USA, LLC) [150]
{2009/12} Fairfield Wind Project in Herkimer, NY (PPM Energy/Atlantic Renewable) [120]
{2009/12} GenWy Wind Farm in Genesee, NY (GenWy Wind, LLC) [478.5]
{2009/12} Jordanville Wind in Herkimer, NY (Jordanville Wind, LLC) [80]
{2009/12} Moresville Energy Center in Delaware, NY (Moresville Energy, LLC) [99]
{2009/12} Ripley-Westfield Wind in Chautauqua, NY (Babcock & Brown LP) [124.8]
{2009/12} St. Lawrence Wind Farm in Jefferson, NY (AES-Acciona Energy NY, LLC) [130]
{2009/12} Steel Winds II in Erie, NY (Steel Winds, LLC) [45]
{2009/12} Tug Hill in Lewis, NY (PPM Roaring Brook, LLC / PPM) [78]
{2009/Q3} Ball Hill Windpark in Chautauqua, NY (Noble Environmental Power, LLC) [90]
{2009/Q3} Marble River II Wind Farm in Clinton, NY (Marble River, LLC) [132.3]
{2009/Q3} Marble River Wind Farm in Clinton, NY (Marble River, LLC) [84]
{2009/Q4} Cape Vincent in Jefferson, NY (BP Alternative Energy NA, Inc.) [210]
{2009/Q4} Cherry Valley Wind Power in Otsego, NY (Reunion Power, LLC) [70]
{2009-2011} Alabama Ledge Wind Farm in Genesee, NY (Alabama Ledge Wind Farm, LLC) [79.2]
{2009-2011} Jericho Rise Wind Farm in Franklin, NY (Jericho Rise Wind Farm, LLC) [79.2]
{2010} Arkwright Summit Wind Farm in Chautauqua, NY (New Grange Wind Farm, LLC) [79.2]
{2010/01} Schoharie Highlands in Schoharie, NY (RP Wind NY, LLC) [70]
{2010/01} Stony Creek Wind Farm in Wyoming, NY (Stony Creek Wind Farm, LLC) [142.5]
{2010/09} Hounsfield Wind in Jefferson, NY (Babcock & Brown LP) [268.8]
{2010/10} Allegany Wind in Cattaraugus, NY (Allegany Wind, LLC) [79]
{2010/10} Western Door Wind in Yates, NY (Western Door Wind, LLC) [100]
{2010/11} Niagara Shore Wind in Niagara, NY (Niagara Shore Winds, LLC) [70.5]
{2010/11} Steuben Wind in Steuben, NY (EC&R Northeast, LLC) [50]
{2010/11} Tonawanda Creek Wind in Genesee, NY (Tonawanda Creek Wind, LLC) [75]
{2010/12} Clayton Wind in Jefferson, NY (PPM Energy, Inc.) [126]
{2010/12} Dutch Gap Wind in Jefferson, NY (PPM Energy, Inc) [250]
{2010/12} Farmersville Windpark in Cattaraugus, NY-PA (Noble Environmental Power, LLC) [100]
{2010/12} Machias I in Cattaraugus, NY (Machias Wind Farm, LLC) [79.2]
{2010/12} Pomfret in Chautauqua, NY (Horizon Wind Energy, LLC) [73.5]
{2010/12} State Line Wind in Chautauqua, NY (Babcock & Brown LP) [124.8]
{2011/09} Concord Wind in Chautauqua, NY (Babcock & Brown LP) [101.2]
{2011/09} Harrigan Hill Wind in Clinton-Ellenburg, NY (Noble Environmental Power, LLC) [100.5]
{2011/12} Crown City Wind Farm in Cortlant, NY (Air Energie TCI, Inc.) [90]
{2011/12} Hamlin Wind Farm in Monroe, NY (Hamlin Wind, LLC) [80]
{2011/12} Leicester Wind in Livingston, NY (Air Energie TCI, Inc.) [57]
{2011/12} State Line Wind II in Chautauqua, NY (Babcock & Brown LP) [124.8]
{2011/12} Stone Church Wind in St. Lawrence, NY (Atlantic Wind, LLC) [150]
{2012/10} Munnsville in Madison, NY (Airtricity Munnsville Wind Farm, LLC) [40]
{2012/12} Madison Wind II in Madison, NY (Horizon Wind Energy, LLC) [79.2]
{2014/01} LI Cable – Phase 1 in Suffolk, NY (Long Island Cable, LLC) [440]
{2015/01} LI Cable – Phase 2a in Suffolk, NY (Long Island Cable, LLC) [220]
{2015/01} Winergy NYC Wind Farm in New York, NY (Winergy Power, LLC) [601]
{2020/01} Offshore Wind in NY – Suffolk, NY (Con Edison/LIPA) [1400]
{TBD} SII Rotterdam Junction in Rotterdam, NY (Schenectady International, Inc.) [9.3]
{None} Cody Rd in Madison, NY (Green Power) [9]
{None} Orion Energy NY I in Herkimer, NY (BP Alternative Energy NA, Inc.) [100]
{None} Prattsburgh Wind Farm in Yates, NY (ECOGEN, LLC) [79.5]

At least 38 wind projects have been withdrawn from the queue.