February 14, 2013
Press releases, Wisconsin

PSC denies Highland Wind Farm application

Public Service Commission, February 14, 2013

MADISON – Today the members of the Public Service Commission decided, on a 2-1 vote, to deny an application of Highland Wind Farm, LLC, for a Certificate of Public Convenience and Necessity to construct a 102.5 Megawatt (MW) Wind Electric Facility in the Towns of Forest and Cylon in St. Croix County.

The majority commissioners determined a clearer record and a better demonstration that noise from the wind turbines would not exceed Commission standards was needed before making a decision to grant a CPCN. Highland Wind Farm, LLC, will be able to reapply to the Commission if an improvement to modeling and additional information is presented in a subsequent application.

Background Information on the Application

In December of 2011, Highland Wind Farm, LLC, filed an application with the Commission for a Certificate of Public Convenience and Necessity (CPCN) to construct a new wind electric generation facility. The project would have included the construction of up to 44 wind turbines, with an electric generating capacity of up to 102.5 megawatts.

Since the application was received, the Commission granted requests to intervene in the proceeding to Clean Wisconsin, Forest Voice, Inc., RENEW Wisconsin, and the Town of Forest, and granted intervenor compensation requests to Clean Wisconsin and Forest Voice. The Commission held multiple technical hearings in Madison; held public hearings in the project area, and accepted expert and public comments online and via U.S. mail. All documents, testimony, and comments submitted in the proceeding are available to the public at the PSC web site, http://psc.wi.gov, by entering docket number 2535-CE-100 in the Electronic Regulatory Filing System.

Thank you, everyone, that contributed to our fight. Now, we fight on for the rest.

Contact: Kristin Ruesch or Matt Pagel, 608-266-9600
Kristin.Ruesch/wisconsin.gov or Matt.Pagel/wisconsin.gov