LOCATION/TYPE

NEWS HOME
(Latest News)



[ exact phrase in "" • results by date ]

[ Google-powered • results by relevance ]

Archive

WHAT TO DO
when your community is targeted

Get weekly updates
RSS

RSS feeds and more

Keep Wind Watch online and independent!

Donate via Stripe

Donate via Paypal

FAQs

Research Links

Selected Documents

Campaign Material

VIDEOS

Photos & Graphics

Store

ALLIES

Wind Watch is a user-supported educational charity, founded in 2005.

• News Watch Home •

Wind-turbine dismantling costs are more than claimed, study reveals 

Credit:  4 August 2025 · Carl Deconinck · brusselssignal.eu ~~

Completely dismantling wind turbines is significantly more expensive than many assume, according to a new Finnish study that cast doubt on the industry’s assumptions about end-of-life costs.

Overall, the Assessment of Decommissioning Costs and Financing Models for Onshore Wind Turbines report from June revealed that the cost for dismantling and landscaping can reach up to close to €1 million.

The report was produced by Eevaleena Häkkinen and Jouko Tuomainen from the Finnish Environment Institute and came to general notice late in July.

These figures underscored the significant financial commitment required for the comprehensive decommissioning and restoration of wind turbine sites.

Other industry reports and some studies have used standardised cost estimates that do not account for local conditions or specific project complexities. These estimates can range from €100,000 to €200,000 per turbine for complete decommissioning, including basic site restoration.

Revenues from recycling materials appear to have been overstated.

It examined in detail the full costs associated with deconstructing wind turbines and restoring the surrounding land, a subject often overshadowed by the sector’s green reputation.

According to the study, decommissioning a single steel tower wind turbine, without removing its concrete foundations, can already cost between €135,400 and €171,900.

If full demolition was undertaken, including the removal of foundations and complete site restoration, though, the costs rose dramatically. For instance, dismantling a hybrid tower wind turbine and excavating the entire foundation can cost between €433,300 and €745,800, the report stated.

The depth of the foundation removal was a further cost driver. Removing a slab foundation to a depth of 2 metres can cost €173,000 to €242,200, while a shallower removal to 1 metre still carries a cost of €144,100 to €190,100.

Local conditions also play a key role in determining the final cost. The report highlighted factors such as the number of turbines, transportation distances, soil bearing capacity and terrain conditions, all of which can significantly affect decommissioning and site restoration expenses.

In addition, the study examined three different landscaping and site restoration scenarios, each with its own financial implications. The most thorough – and most expensive – approach involved the complete removal of structures, followed by the replacement of excavated areas with new soil masses, at a cost ranging between €415,400 and €700,500 per steel tower turbine.

While the potential for revenue from recycling materials such as steel, aluminium, and copper offers a partial offset, the report warned against over-reliance on scrap value. Market volatility, coupled with transport and handling costs, meant such revenues may fall short of covering the full dismantling costs, it said.

“Prices of metals can vary significantly, and the actual revenue from selling recycled materials may not cover the costs of dismantling and site restoration,” the report authors cautioned.

Another often-overlooked element was the management of hazardous materials, such as oil residues and insulation components, which added to both cost and regulatory complexity.

The decommissioning process generally must also adhere to strict environmental and safety regulations, ensuring that the land is either restored to its original condition or repurposed responsibly.

The challenge was compounded by the increasing size of modern turbines. The report noted that the average hub height of turbines built between 1993 and 2023 was 137 metres, rising to 146 metres for turbines constructed between 2016 and 2023.

The growing size of these machines meant that more labour, machinery and logistical co-ordination was required for safe and compliant removal, it said.

Finally, differences in national and regional regulations, particularly in relation to environmental standards, could influence the financial modelling of decommissioning projects.

Countries or regions with stricter restoration requirements will inevitably face higher costs, the report concluded.

Source:  4 August 2025 · Carl Deconinck · brusselssignal.eu

This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.

The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.

Wind Watch relies entirely
on User Contributions
   Donate via Stripe
(via Stripe)
Donate via Paypal
(via Paypal)

Share:

e-mail X FB LI BS M TS TG Share


• News Watch Home •

Get the Facts
CONTACT • DONATE • PRIVACY • ABOUT • SEARCH
© National Wind Watch, Inc.
Use of copyrighted material adheres to Fair Use.
"Wind Watch" is a registered trademark.

 Follow:

Wind Watch on X Wind Watch on Facebook Wind Watch on Linked In

Wind Watch on Bluesky Wind Watch on Mastodon Wind Watch on Truth Social