LOCATION/TYPE

NEWS HOME
(Latest News)


[ exact phrase in "" • results by date ]

[ Google-powered • results by relevance ]

Archive

WHAT TO DO
when your community is targeted

Get weekly updates
RSS

RSS feeds and more

Keep Wind Watch online and independent!

Donate via Stripe

Donate via Paypal

FAQs

Research Links

Selected Documents

Campaign Material

VIDEOS

Photos & Graphics

Store

ALLIES

Wind Watch is a user-supported educational charity, founded in 2005.

• News Watch Home •

NJ mayors call for deferral of offshore wind contracts amid soaring costs, health risks, and turbine supply failures 

Credit:  By Jim Lonergan · Published September 29, 2024 at tapinto.net ~~

On Tuesday, the mayors of Sea Girt, Manasquan, Wall Township, and Howell, the towns targeted for offshore wind cable transmission lines, sent a letter to the New Jersey Board of Public Utilities (NJBPU) urging the board to indefinitely defer any award of offshore contracts related to these transmission lines.

The letter specifically outlines, “We are aware that the NJBPU has petitioned the Federal Energy Regulatory Commission (FERC) to reduce the approved Return on Equity (ROE) on the initial phase of the Larabee Pre-built Infrastructure (PBI) project due to concerns with the cost impact of this project on transmission rates. The same concern would apply to any PBI award which can be expected to cost multiples of the current $1.2B cost already approved for this project.”

The reasoning behind this petition is NJBPU’s concern over how the current ROE might lead to even higher transmission rates for ratepayers. Essentially, the NJBPU is asking FERC to reduce the profit margin for investors or developers involved in the project because they believe the costs may even further unfairly burden ratepayers with increased transmission charges.

The rising and realistic costs of offshore wind energy are not new. We’ve collaborated with experts and written extensively on this ongoing issue. For more insights, click here for a deep look at the cost challenge and impact to NJ Ratepayers, and here for our story: NJ Wind Energy: High Hopes, Higher Costs.

A key concern raised in the letter is the NJBPU’s bid solicitation process. Developers can win project bids, claim rising costs and insufficient ROE, and prompt the state to reopen bidding at higher rates. This cycle increases costs for taxpayers and ratepayers. Currently in its fourth round, NJBPU’s solicitation process has escalated costs (taxpayers who will be subsidizing the costs and ratepayers who will see it in rising energy bills each month) with each bid. Ørsted, a prominent wind developer, withdrew from its offshore contract in late 2023, paying $125 million of a $300 million break-up fee, despite more favorable terms offered by a new solicitation round.

The letter also references the challenges faced by Leading Light, a developer “who has requested a stay of its approved BPU order and may not be able to proceed due to the lack of a viable wind turbine supplier and is being challenged in a ratepayer appeal.” As we highlighted in our Offshore Wind Series, this echoes the global supply chain realities of an industry that has not yet been built to handle projects at this scale. According to RTO Insider, over almost two decades, Europe is now able to produce 30 GW of wind power, and Asia between 20-25 GW. Yet in one mandate, the state of New Jersey is targeting 11 GW by 2040. The US has approximately 1 GW of operational offshore wind energy with another 40-50GW in some form of development/planning. Recent turbine failures, such as those at GE Nantucket and Dogger Bank, further strain the wind turbine supply chain.

Additionally, the letter expressed serious concerns about the potential health and safety risks of routing up to 6,400 MW of high-voltage cables through residential neighborhoods, as well as the disruption to public activities. In an earlier story, we specifically addressed the transmission lines and risks.

If you are concerned or simply have questions, this Tuesday, October 1st, at 6:30PM, after months of local elected leaders trying to have the NJBPU answer the many questions residents have, the meeting is set. Click to sign-up for the in-person or via Zoom event: https://us06web.zoom.us/webinar/register/WN_Pyl5A2v2SrmKfCZsfd3Nyg#/registration

Source:  By Jim Lonergan · Published September 29, 2024 at tapinto.net

This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.

The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.

Wind Watch relies entirely
on User Contributions
   Donate via Stripe
(via Stripe)
Donate via Paypal
(via Paypal)

Share:

e-mail X FB LI BS M TS TG Share


• News Watch Home •

Get the Facts
CONTACT • DONATE • PRIVACY • ABOUT • SEARCH
© National Wind Watch, Inc.
Use of copyrighted material adheres to Fair Use.
"Wind Watch" is a registered trademark.

 Follow:

Wind Watch on X Wind Watch on Facebook Wind Watch on Linked In

Wind Watch on Bluesky Wind Watch on Mastodon Wind Watch on Truth Social