LOCATION/TYPE

NEWS HOME

[ exact phrase in "" • results by date ]

[ Google-powered • results by relevance ]


Archive
RSS

Add NWW headlines to your site (click here)

Get weekly updates

WHAT TO DO
when your community is targeted

RSS

RSS feeds and more

Keep Wind Watch online and independent!

Donate via Stripe

Donate via Paypal

Selected Documents

All Documents

Research Links

Alerts

Press Releases

FAQs

Campaign Material

Photos & Graphics

Videos

Allied Groups

Wind Watch is a registered educational charity, founded in 2005.

News Watch Home

Regulators grant critical approval for Dominion wind farm 

“The magnitude of this project is so great that it will likely be the costliest project being undertaken by any regulated utility in the United States. And the electricity produced by this Project will be among the most expensive sources of power — on both a per kilowatt of firm capacity and a per megawatt-hour basis — in the entire United States,” the order said.

Credit:  By Sarah Rankin, AP | December 15, 2022 | washingtonpost.com ~~

Virginia regulators granted a critical approval Thursday for Dominion Energy’s plans to construct and operate a 176-turbine wind farm in the Atlantic Ocean.

The State Corporation Commission effectively signed off on an agreement Dominion reached this fall with the Virginia attorney general and several other parties, in which the company agreed to implement several consumer protections in connection with the Coastal Virginia Offshore Wind project.

“We thank the Commission for its approval and appreciate the collaboration of the parties involved to reach an agreement that advances offshore wind and the clean energy transition in Virginia,” the Richmond-based company said in a statement. “Coastal Virginia Offshore Wind has many benefits for our customers. It is fuel free, emissions free, diversifies our energy mix and is a transformative economic development opportunity for Hampton Roads and Virginia.”

In its order, the commission also issued a warning about the impact the project will have on the electricity bills of Dominion’s captive electric utility customers.

“The magnitude of this project is so great that it will likely be the costliest project being undertaken by any regulated utility in the United States. And the electricity produced by this Project will be among the most expensive sources of power – on both a per kilowatt of firm capacity and a per megawatt-hour basis – in the entire United States,” the order said.

Dominion filed its application to build and recover the costs of the project with the State Corporation Commission last year. That kicked off a lengthy process before the regulatory agency, one that has included voluminous filings and an evidentiary hearing in May.

The commission initially signed off on the project in August, but it included a consumer protection provision – a performance guarantee – that Dominion strenuously objected to, saying it would kill the project.

Several parties to the SCC proceeding began to hash out a compromise, announcing a proposed agreement in late October that did away with the performance guarantee but does include performance reporting requirements and provisions laying out a degree of construction cost sharing.

The agreement now approved by the SCC calls for a cost-sharing arrangement for any overruns beyond the estimated $9.8 billion price tag. The company would cover 50% of construction costs between the range of $10.3-$11.3 billion and 100% of costs between $11.3-$13.7 billion. If construction costs were to exceed $13.7 billion, the issue would go back to the commission.

The proposal would not require the company to guarantee certain energy production levels, like the SCC had initially ordered. Rather, Dominion will have to report average net capacity factors annually and “provide a detailed explanation of the factors contributing to any deficiency.” Capacity factor is a measure of how often a generating facility runs during a period of time.

The commission will also have the continuing authority to inspect Dominion’s expenditures on the project to ensure they are reasonable and prudent under state law.

The project, which will be located about 27 miles off the coast of Virginia Beach, has drawn broad support from local officials, policymakers, business groups and trade unions, who say it will help fight climate change and create jobs.

The company already has a two-turbine pilot project up and running. The 2.6-gigawatt, utility-scale project’s schedule calls for an in-service date of late 2026 or early 2027. Dominion expects the project to generate enough clean energy to power up to 660,000 homes.

Thursday’s SCC order noted that while Dominion estimates the capital cost of the project to be nearly $10 billion, total project costs, including financing, are estimated to be approximately $21.5 billion.

Source:  By Sarah Rankin, AP | December 15, 2022 | washingtonpost.com

This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.

The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.

Wind Watch relies entirely
on User Funding
   Donate via Stripe
(via Stripe)
Donate via Paypal
(via Paypal)

Share:

e-mail X FB LI M TG TS G Share


News Watch Home

Get the Facts
CONTACT DONATE PRIVACY ABOUT SEARCH
© National Wind Watch, Inc.
Use of copyrighted material adheres to Fair Use.
"Wind Watch" is a registered trademark.

 Follow:

Wind Watch on X Wind Watch on Facebook Wind Watch on Linked In

Wind Watch on Mastodon Wind Watch on Truth Social

Wind Watch on Gab Wind Watch on Bluesky