New wind farms threaten £2.5bn ‘constraints’ bill for consumers
Credit: Emily Gosden, Energy Editor | The Times | Tuesday June 29 2021 | www.thetimes.co.uk ~~
Translate: FROM English | TO English
Translate: FROM English | TO English
Consumers face paying up to £2.5 billion a year to switch off new wind farms and other power plants because transmission cables will not be built quickly enough to carry the electricity they generate.
National Grid’s control room, which is responsible for keeping the lights on, pays power plant owners to “constrain” output when the network does not have enough capacity to transmit their electricity to where it is needed. It also pays for power plants elsewhere in the network to fire up and replace the generation that has been constrained.
These “constraint costs” amount to about £500 million a year, but new estimates from National Grid’s Electricity System Operator forecast that they will at least double and could increase five-fold to £2.5 billion within
This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.
Wind Watch relies entirely on User Contributions |
(via Stripe) |
(via Paypal) |
Share: