June 16, 2021
South Dakota

Low bid to repair 60-plus miles of Codington County roads comes in at $8.1 million

Grant Evans | Watertown Public Opinion | Jun. 15, 2021 | www.thepublicopinion.com

Roads damaged while building a wind farm in Codington County will cost at least $8.1 million to repair, according to bids opened by county commissioners during their Tuesday meeting.

NextEra, which oversaw the wind energy project, will cover the cost.

Commissioners opened and reviewed three bids for the work:

No action was taken, but commissioners will revisit the topic soon to award the bid.

The county expected the work to improve 60-odd miles of roads could cost near $11.5 million. That’s a total that was discussed at previous commission meetings.

The roads were damaged when NextEra built the Crowned Ridge 1 and 2 wind energy projects in the eastern third of Codington County. That’s why the Florida-based company is agreeable to paying for the damage.

The project will include nearly 85,000 tons of asphalt concrete composite as the roads are improved.


URL to article:  https://www.wind-watch.org/news/2021/06/16/low-bid-to-repair-60-plus-miles-of-codington-county-roads-comes-in-at-8-1-million/