LOCATION/TYPE

NEWS HOME

[ exact phrase in "" • results by date ]

[ Google-powered • results by relevance ]



Archive
RSS

Add NWW headlines to your site (click here)

Get weekly updates

WHAT TO DO
when your community is targeted

RSS

RSS feeds and more

Keep Wind Watch online and independent!

Donate via Paypal

Donate via Stripe

Selected Documents

All Documents

Research Links

Alerts

Press Releases

FAQs

Campaign Material

Photos & Graphics

Videos

Allied Groups

Wind Watch is a registered educational charity, founded in 2005.

News Watch Home

Dundonnell wind farm stops production after blade falls off turbine 

Credit:  Giles Parkinson | Renew Economy | 7 October 2020 | reneweconomy.com.au ~~

More problems have emerged at the massive new Dundonnell wind farm in Victoria, which has stopped production after a blade fell off one of the project’s 80 newly installed Vestas turbines.

The incident on October 5 – which occurred around 7.30pm on Monday night on a turbine that was operating at the time – quickly brought production at all turbines at the Dundonnell wind farm to a halt. The facility has been operating at less than half of its rated 336MW capacity because of constraints imposed by the Australian Energy Market Operator due to unspecified commissioning issues.

In a statement, project owner Tilt Renewables said “a single blade separated from the hub of a turbine and fell to the ground. There were no injuries caused by the incident and there is no damage to any other property or wind turbines to report.”

It went on to say that all wind turbines at the site are currently removed from service whilst an investigation and assessment of the damage is undertaken.

“A root cause analysis will be completed in conjunction with the wind turbine manufacturer, Vestas, which will inform the assurance process on the other turbines prior to these being returned to service,” it said.

“Appropriate commercial and contractual provisions are in place to mitigate the effects of an incident of this nature and at this time it is not expected to materially impact the business.”

Tilt Renewables has already foreshadowed a significant reduction in earnings for the current financial year due to the delays in commissioning Dundonnell, which it had hoped would be fully operational by now.

Just over a week ago, Tilt had announced that the project had been allowed to use all its 80 turbines, and move to a new “hold point” of 150MW. It said then it was confident of reaching full capacity by the end of the calendar year.

Nearby resident and prominent wind energy critic Hamish Cumming, who supplied the above photo, said in an email to RenewEconomy that there had been questions about whether the blades had been fatigue tested.

“Others will follow if it is the fatigue issue. This is also a work cover issue for farmers,” he said. Tilt says that claim is nonsense and the turbines are fully compliant and fully tested. Its certification can be found here.

It is not the first time a blade has fallen from a Vestas turbine in Victoria. Last September, a blade fell from a turbine at the Lal Lal wind farm near Moorabool, an incident that Vestas attributed at the time to a lightning strike.

There were no reports of lightning near Dundonnell on Monday. Production at Lal Lal resumed a day after its blade incident, but it is not clear when production will resume at Dundonnell.

Last month, a similar incident occurred in Ohio, where a blade of a Vestas 150 4.2MW turbine – the same model at Dundonnell – broke off at the 125MW Timber Road 4 project.

Vestas has sent a team to the Dundonnell site to investigate the cause of the incident.

Source:  Giles Parkinson | Renew Economy | 7 October 2020 | reneweconomy.com.au

This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.

The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.

Wind Watch relies entirely
on User Funding
   Donate via Paypal
(via Paypal)
Donate via Stripe
(via Stripe)

Share:

e-mail X FB LI TG TG Share

Tag: Accidents


News Watch Home

Get the Facts
CONTACT DONATE PRIVACY ABOUT SEARCH
© National Wind Watch, Inc.
Use of copyrighted material adheres to Fair Use.
"Wind Watch" is a registered trademark.

 Follow:

Wind Watch on X Wind Watch on Facebook

Wind Watch on Linked In Wind Watch on Mastodon