LOCATION/TYPE

NEWS HOME

[ exact phrase in "" • results by date ]

[ Google-powered • results by relevance ]


Archive
RSS

Add NWW headlines to your site (click here)

Get weekly updates

WHAT TO DO
when your community is targeted

RSS

RSS feeds and more

Keep Wind Watch online and independent!

Donate via Stripe

Donate via Paypal

Selected Documents

All Documents

Research Links

Alerts

Press Releases

FAQs

Campaign Material

Photos & Graphics

Videos

Allied Groups

Wind Watch is a registered educational charity, founded in 2005.

News Watch Home

Tall wind turbines in Botetourt will pose no hazard to aircraft, FAA determines 

Credit:  Laurence Hammack | The Roanoke Times | August 6, 2020 | roanoke.com ~~

Making tall turbines 130 feet taller will not endanger passing aircraft, the Federal Aviation Administration has determined.

In a step forward for a proposed wind farm in Botetourt County, the FAA found this week that turbines reaching as far as 680 feet into the sky from the top of a mountain would “not constitute a hazard to air navigation.”

It was the second time the agency has determined that the renewable energy project, to be located in a remote and rural spot about 17 miles from the nearest airport, would not pose a threat.

In 2016, it cleared plans to build up to 25 turbines, each one as tall as 550 feet. But construction never started as the developer, Apex Clean Energy of Charlottesville, spent the next three years looking for a customer to buy its power.

By the time a deal was reached with Virginia and Dominion Energy, which will purchase the power and then sell it to the state, new technology allowed fewer – although taller – turbines to produce the same electrical output.

Apex then redrew its plans to include up to 22 turbines as tall as 680 feet atop North Mountain, which required a new round of permits.

The Botetourt County Board of Supervisors approved a special use permit in May. Apex must still obtain a permit from the Virginia Department of Environmental Quality before it can start construction of what will be the state’s first on-shore, utility-scale wind farm.

Work could begin this winter, Apex spokeswoman Natasha Montague said Thursday, and be completed by the end of 2021.

A final decision has not been made on the type of turbine Apex will use, which will dictate the exact number and height of the structures. Montague wrote in an email that “we are down to a short list of options.”

As part of DEQ’s process to amend a permit first granted in 2017, public comments will be accepted though Aug. 10. Apex will then respond to the comments. After that, DEQ will have 90 days to act.

Dubbed Rocky Forge, the project will convert wind into enough electricity to serve up to 20,000 homes, Apex has said. In the end, though, the power will be sold to Virginia as part of a wind and solar package that will assist the state in reaching its goal of using green energy for at least 30% of the electricity consumed by state agencies by 2022.

Long-term plans call for Virginia’s two largest utilities, Dominion and Appalachian Power Co., to be completely free of fossil-fuel generated power by 2050.

As a condition for its approval, the FAA said the turbines should be marked with white paint and equipped with synchronized red lights to make them more visible to pilots.

Although that’s likely to upset some wind farm opponents – who say the giant windmills will be an eyesore and a threat to the environment – those concerns fell outside of the aviation agency’s purview.

DEQ’s review will focus on the wind farm’s effect on the surrounding mountainous terrain and the plants and animals that inhabit it. In granting a permit in 2017, DEQ required Apex to turn the turbines off from dusk to dawn in the warmer months, to protect flying bats that might otherwise be killed by the spinning blades.

As part of its evaluation, the FAA called for public comments. There were none. But the Department of Defense did note that the wind farm is near or in an area used for its aircraft training exercises.

While the turbines are not expected to interfere with low-flying military jets, the Defense Department requested that the lighting system be compatible with night vision goggles worn by its pilots.

Source:  Laurence Hammack | The Roanoke Times | August 6, 2020 | roanoke.com

This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.

The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.

Wind Watch relies entirely
on User Funding
   Donate via Stripe
(via Stripe)
Donate via Paypal
(via Paypal)

Share:

e-mail X FB LI M TG TS G Share


News Watch Home

Get the Facts
CONTACT DONATE PRIVACY ABOUT SEARCH
© National Wind Watch, Inc.
Use of copyrighted material adheres to Fair Use.
"Wind Watch" is a registered trademark.

 Follow:

Wind Watch on X Wind Watch on Facebook Wind Watch on Linked In

Wind Watch on Mastodon Wind Watch on Truth Social

Wind Watch on Gab Wind Watch on Bluesky