LOCATION/TYPE

NEWS HOME

[ exact phrase in "" • results by date ]

[ Google-powered • results by relevance ]


Archive
RSS

Add NWW headlines to your site (click here)

Get weekly updates

WHAT TO DO
when your community is targeted

RSS

RSS feeds and more

Keep Wind Watch online and independent!

Donate via Stripe

Donate via Paypal

Selected Documents

All Documents

Research Links

Alerts

Press Releases

FAQs

Campaign Material

Photos & Graphics

Videos

Allied Groups

Wind Watch is a registered educational charity, founded in 2005.

News Watch Home

Start-up delays take puff out of wind projects 

Credit:  Perry Williams, Senior Business Writer | The Australian Business Review | Friday, January 31, 2020 | www.theaustralian.com.au ~~

Some of Australia’s biggest wind farms face delays in bringing their full capacity into the national power market, pushing out further wholesale price relief amid a slowdown in renewable projects connecting to the grid.

The only four wind farms that began operations last year were still progressing through the ­“energising” and commissioning phases of start-up, in a slower process than many in the market ­expected, consultancy ITK Services said.

That means a large volume of energy will be delivered to market later than anticipated and commissioning timelines for future wind projects might be wrong, based on the time lag hitting the sector now.

“Both impacts are likely to cause wholesale prices to be higher than they would otherwise be,” ITK analyst Ben Willacy said.

The Murra Warra wind farm in northwestern Victoria and the Lincoln Gap facility near Port ­Augusta in South Australia have been in the commissioning phase for nine months and eight months respectively.

Victoria’s Lal Lal wind farm near Ballarat and Queensland’s giant Coopers Gap wind unit were operating at less than half their notional capacity seven months after energising, ITK said, referencing new figures released by a separate consultancy, Global-ROAM.

The delays are likely to be a mix of longer construction timelines than seen in the previous boom-like conditions in the past few years.

It may also reflect a clampdown by the grid operator to ­ensure new renewable projects do not lead to further congestion ­issues after rapid growth in new wind and solar projects in areas not always close to existing transmission.

“The reasons for the slow time frames will likely be a mix of both systemic and assets specific ­issues,” Mr Willacy said.

“But it’s enough to suggest the beginnings of a trend, especially considering these four wind farms are the only ones in the national electricity market to have started operations in 2019.”

And with 2700MW of wind ­capacity under construction, sliding timelines could result in a price spike.

Ultimately, ITK said it expected big wind farms like Victoria’s Stockyard Hill and the Bulgana Green Energy Hub in South Australia may have to wait until 2021 to send their “full complement” of energy into the power grid.

“Given average construction time frames, we expect all 2700MW to be energised in 2020, but it looks increasingly unlikely that they (the wind farms) will be fully commissioned this year,” ITK said.

The slowing pace of renewable projects has sparked concern among some big-name investors, including the influential QIC, which cited figures saying just 151MW of new generation was committed in the current financial year, from two projects, compared to 4300MW across 46 plants in the 2019 financial year.

However, federal Energy Minister Angus Taylor also noted that 6300MW of new renewables ­capacity was added in 2019, which marked a 24 per cent jump on the previous record set the prior year.

Australia requires at least 30,000MW of solar and wind to replace coal generation by 2040, and 47,000MW should more ­aggressive pollution cuts be required in response to the climate change crisis, Australian Energy Market Operator data shows.

Source:  Perry Williams, Senior Business Writer | The Australian Business Review | Friday, January 31, 2020 | www.theaustralian.com.au

This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.

The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.

Wind Watch relies entirely
on User Funding
   Donate via Stripe
(via Stripe)
Donate via Paypal
(via Paypal)

Share:

e-mail X FB LI M TG TS G Share


News Watch Home

Get the Facts
CONTACT DONATE PRIVACY ABOUT SEARCH
© National Wind Watch, Inc.
Use of copyrighted material adheres to Fair Use.
"Wind Watch" is a registered trademark.

 Follow:

Wind Watch on X Wind Watch on Facebook Wind Watch on Linked In

Wind Watch on Mastodon Wind Watch on Truth Social

Wind Watch on Gab Wind Watch on Bluesky