LOCATION/TYPE

NEWS HOME

[ exact phrase in "" • results by date ]

[ Google-powered • results by relevance ]



Archive
RSS

Add NWW headlines to your site (click here)

Get weekly updates

WHAT TO DO
when your community is targeted

RSS

RSS feeds and more

Keep Wind Watch online and independent!

Donate via Stripe

Donate via Paypal

Selected Documents

All Documents

Research Links

Alerts

Press Releases

FAQs

Campaign Material

Photos & Graphics

Videos

Allied Groups

Wind Watch is a registered educational charity, founded in 2005.

News Watch Home

One Willmar wind turbine could stand still for weeks awaiting replacement part 

Credit:  By Shelby Lindrud | West Central Tribune | www.wctrib.com ~~

WILLMAR – The Willmar Municipal Utilities Commission last week received an update from staff about problems with Wind Turbine 4. It is inoperable due to a broken hydraulic pitch control board failure, which moves the turbine’s blades.

“It would spin out of control, which wouldn’t be a good thing,” said Brian Hoover, power plant foreman, during a report Feb. 12 to the Willmar Municipal Utilities Commission.

The part cannot be repaired, and a new one could take nearly 14 weeks to arrive.

“We foresee it standing still for a while, until that part comes in,” Hoover said.

One of the main issues facing Willmar Municipal Utilities when repairing and sourcing parts for the turbines is they are foreign-built. Also, DeWind, that company that supplied the turbines, no longer does business in the United States.

Staff is looking into developing a database of turbine resources, so when a part or service is needed, they’ll have a list of possible suppliers to turn too.

Wind Turbine 3, on the other hand, had a very good January, producing almost 400,000 kilowatt-hours of power.

Bids awarded

The Willmar Municipal Utilities Commission last week also awarded bids for two major projects.

The commission awarded a $377,980 contract to Ziegler Power Systems to complete necessary exhaust particulate upgrades to four diesel generators.

The generators are only used for emergency power production, and for the past few years have only been run during tests. Once the upgrades have been completed, the generators will be in compliance both with the Midcontinent Independent System Operator, which oversees a large portion of the nation’s electrical grid, and the Environmental Protection Agency.

While the EPA is not requiring emergency production diesel generators to meet these exhaust requirements, MISO is.

A bid was also awarded Feb. 12 for the Priam substation project. Siemens Industry Inc. will provide a 69-kilovolt circuit breaker for the planned substation at a cost of $35,860.

The total project to construct the substation along state Highway 23 southwest of Willmar is estimated to cost $4.5 million.

Source:  By Shelby Lindrud | West Central Tribune | www.wctrib.com

This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.

The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.

Wind Watch relies entirely
on User Funding
   Donate via Stripe
(via Stripe)
Donate via Paypal
(via Paypal)

Share:

e-mail X FB LI M TG TS G Share

Tag: Accidents


News Watch Home

Get the Facts
CONTACT DONATE PRIVACY ABOUT SEARCH
© National Wind Watch, Inc.
Use of copyrighted material adheres to Fair Use.
"Wind Watch" is a registered trademark.

 Follow:

Wind Watch on X Wind Watch on Facebook Wind Watch on Linked In

Wind Watch on Mastodon Wind Watch on Truth Social

Wind Watch on Gab Wind Watch on Bluesky