Peel Energy has been refused permission on appeal for the 21.6MW Garleffan wind farm in East Ayrshire, Scotland.
Scottish government officials agreed with an original local authority ruling in 2016 that the project near New Cumnock would have unacceptable visual and landscape impacts.
“I consider that the proposed turbines have not been sited and designed to minimise visual impact,” said the government reporter.
Peel had argued that other nearby wind farms, including Hare Hill, would make the project acceptable in landscape terms but officials disagreed.
“I find the adverse landscape impacts … would be more significant than predicted,” said the reporter.
Peel originally filed to build Garleffan in March 2013 as a nine-turbine wind farm. Tips were set at 135 metres on what is a former surface coal mine.
This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.
Wind Watch relies entirely on User Funding |
![]() (via Paypal) |
![]() (via Stripe) |
Share:
Tag: Victories |