LOCATION/TYPE

NEWS HOME

[ exact phrase in "" • results by date ]

[ Google-powered • results by relevance ]


Archive
RSS

Add NWW headlines to your site (click here)

Get weekly updates

WHAT TO DO
when your community is targeted

RSS

RSS feeds and more

Keep Wind Watch online and independent!

Donate via Stripe

Donate via Paypal

Selected Documents

All Documents

Research Links

Alerts

Press Releases

FAQs

Campaign Material

Photos & Graphics

Videos

Allied Groups

Wind Watch is a registered educational charity, founded in 2005.
»» Search…

News Watch Home

Wind farm connection stopped over lack of planning permission 

Credit:  Tim Healy | Farm Ireland | May 12, 2017 | www.independent.ie ~~

Share:

e-mail X FB LI M TG TS G Share


A farmer has got High Court orders halting works to connect a windfarm in Co Sligo to an electricity substation in Co Leitrim.

It follows Ms Justice Marie Baker’s ruling that An Bord Pleanala incorrectly decided the works do not require planning permission.

The orders restrains Kilronan WindFarm Ltd and Derrysallagh WindFarm Ltd (DWF) continuing to lay underground cables to connect a planned 12 turbine wind farm at Derrysallagh to an ESB substation at Garvagh Glebe, Co Leitrim .

About 70pc of the cables are already laid and those do not have to be removed, Ms Justice Baker said.

She made the orders after upholding arguments on behalf of Patrick Daly the grid connection works could not begin until there is permission for the wind farm development as a whole, including the grid works.

Mr Daly had in May 2012 lodged a submission expressing concerns about noise and visual impact of the turbines, loss of amenity value and impact on his grazing rights.

DWF has an electricity generation licence dated February 2016 and is authorised to distribute electricity within the State, the judge noted.

The laying of underground cables was generally exempt development unless that falls within certain provisions of the Planning and Development Act, in which case it requires an Environmental Impact Assessment or Appropriate Assessment.

Source:  Tim Healy | Farm Ireland | May 12, 2017 | www.independent.ie

This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.

The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.

Wind Watch relies entirely
on User Funding
   Donate via Stripe
(via Stripe)
Donate via Paypal
(via Paypal)


News Watch Home

CONTACT DONATE PRIVACY ABOUT SEARCH
© National Wind Watch, Inc.
Use of copyrighted material adheres to Fair Use.
"Wind Watch" is a registered trademark.