State’s first wind farm being disassembled  

Credit:  By VICKI ROCK, Nov 14, 2016, dailyamerican.com ~~

The first wind farm in Pennsylvania is being dismantled.

Donald Decker and his brother Robert Decker each had four windmills on their farms near Garrett.

“I was told that they are deteriorating,” Donald Decker said. “They were supposed to do maintenance weekly, but in the winter sometimes they didn’t plow for a month.”

That group of wind turbines, called the Green Mountain Wind Energy Center, was originally owned by National Wind Power of the United Kingdom and was operated by NextEra Energy Resources, based in Florida. A company spokesman was not available for comment Monday.

Energy from the wind farm was sold by Green Mountain Energy, based in Texas. The eight 200-foot windmills were dedicated in the fall of 2000. The 10.4-megawatt plant could produce enough electricity to serve the average needs of about 3,300 homes.

Bill Lehman, planner with the Somerset County Planning Commission, said that wind farm was built before Somerset County had a windmill ordinance, so the company did not have to report the decommissioning. At least two other wind farms in the county were also built before the ordinance, which was approved in 2004.

When the windmills were erected, the Deckers were told that they would last about 20 years.

“Well, this is close to that,” he said. “I’d sooner see them stay, but there’s nothing we can do about it.”

582a8163303c2-image

Mike Petenbrink, of Garrett, photographed one of the turbines coming down.

“They torched it and cut part of it off, like dropping a tree,” he said. “An excavator pulled it with a cable and they let it drop. Down it went. Everything runs its course; I remember them saying the lifespan was about 20 years.”

Joseph Romesberg, of Meyersdale, remembers that he and his parents, Fred and Ruth, went to see the windmills being assembled. His father is no longer living.

“It is a bit depressing to see them come down,” he said. “We were excited when they went up because they were the first in this area. It’s sort of sad that they are coming down and to know how many years it has been.”

NextEra also operates wind farms near Somerset, Meyersdale and Mill Run, Fayette County, where a turbine collapsed in 2014, injuring no one. There are more than 180 turbines in Somerset County, including 68 at the Twin Ridges Wind Farm in Southampton, Northampton, Larimer and Greenville townships.

Lehman said the Mason-Dixon Wind Project, in Larimer and Southampton townships, has been approved for 20 wind turbines. The project is to interconnect with the Twin Ridges substation. EverPower Wind Holdings is the developer.

Source:  By VICKI ROCK, Nov 14, 2016, dailyamerican.com

This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.

Wind Watch relies entirely
on User contributions

Share:


« Later PostNews Watch HomeEarlier Post »

Get the Facts Follow Wind Watch on Twitter

Wind Watch on Facebook

Share

CONTACT DONATE PRIVACY ABOUT SEARCH
© National Wind Watch, Inc.
Use of copyrighted material adheres to Fair Use.
"Wind Watch" is a registered trademark.
Formerly at windwatch.org.

HOME
Follow Wind Watch on Twitter

Wind Watch on Facebook

Share