Council wins £10,000 costs in wind turbine appeal battle
Credit: Lesley Tate, Senior Reporter | Craven Herald | www.cravenherald.co.uk ~~
Translate: FROM English | TO English
Translate: FROM English | TO English
Costs of almost £10,000 were awarded to Craven District Council following its long fight with an energy company wanting to build wind turbines near Gargrave.
EnergieKontor UK finally admitted defeat in February when its appeal against the council’s decision to refuse planning permission to build three 328ft (100m) high turbines at Brightenber Hill, near East Marton, was rejected by the secretary of state in charge of planning.
It followed an eight year battle by Craven councillors and pressure group, Friends of Craven Landscape to stop turbines being built at the site.
A spokesman for Craven District Council said: “After making a claim we received a payment of £9,427 from the Planning Inspectorate for the reimbursement of costs that were directly incurred from the re-determined planning appeal. The Planning Inspectorate agreed to pay these costs as they acknowledged that they made an error with the initial appeal decision.”
This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.
Wind Watch relies entirely on User Contributions |
(via Stripe) |
(via Paypal) |
Share: