June 17, 2016
Indiana

Local judge bows out of wind farm battle

By JAMES SPRAGUE, Friday, June 17, 2016, www.newsexaminer.com

The local battle between a group of Fayette County landowners, the county and Big Wind will now find itself with a new face in the game.

A new judge.

Fayette Circuit Judge Beth A. Butsch, who had been presiding in the court case involving Fayette County Commissioners, Whitewater Wind LLC – aka NextEra Energy Resources – and the group of 34 county landowners challenging the legitimacy of the county’s wind turbine decommissioning agreement with NextEra, recused herself this week from the case.

Her recusal means a special judge will now be appointed in the case, where the landowner group claims that the county’s decommissioning agreement for wind turbines in the proposed Whitewater Wind Farm project does not adhere to the county’s zoning ordinance.

Butsch recused herself from the case Tuesday, in an order filed by her court with the Fayette County Clerk’s Office.

“The undersigned recuses herself as Judge in this case to avoid the appearance of impropriety,” Butsch stated in the order. “The Court now orders the Clerk of the Fayette Circuit Court to assign a special judge in this matter.” As of Thursday afternoon, a judge had yet to be selected, per case records.

The complaint filed by the landowners against the project – which would see approximately 43 wind turbines placed in Fayette County, specifically in Posey and Fairview townships, and the county

The project, slated to span Fayette, Henry and Rush counties and begin construction this year, would see approximately 43 wind turbines place in Fayette County, specifically in Posey and Fairview townships.

The complaint filed by the landowners focuses specifically on an addendum to the decommissioning agreement the county and NextEra Energy signed off on for the project in September 2015, which was supposed to clarify language in the contract for how long and how much the security bond required by the energy company would be for regarding decommissioning wind turbines at the end of the project.

According to the plaintiffs, a conforming decommissioning agreement – per county zoning ordinances – “was not submitted at the time of filing of the Special Exception Application,” along with the plan “submitted at the time of the filing of the Special Exception Application failed to include a contractor cost estimate for demolition and removal of the WECS facility,” along with failing “to provide financial assurance at least equal to the demolition and removal contractor cost estimate that will continue for the project life of the WECS facility.”

The complaint goes on to state that the decision by county commissioners to approve the original decommissioning plan – without the addendum – was “arbitrary and capricious” because they had insufficient information at that time, due to the “failure of Whitewater Wind LLC to timely file the required contractor cost estimate and financial assurance concurrently with the Special Exception Application or prior to approval of the Decommissioning Plan” by commissioners.

The decommissioning agreement between the two parties has been called into question several times since August 2015, when NextEra’s special exception applications for construction of the Whitewater Wind Farm project were heard at the county’s Board of Zoning Appeals hearing.

Among the concerns from some included the ambiguous language in the original decommissioning agreement and the length of time listed for the security bonds required to pay for the decommissioning of the wind turbines – which appeared to much for a much shorter period of time than the estimated lifespan of the wind farm project, which is required by Fayette County zoning code.

The projected lifespan of the Whitewater Wind Farm, as previously stated by NextEra project manager Jeremy Ferrell, is 30 years.

NextEra, in August 2015, agreed to sign off on an addendum by the county to the decommissioning contract, which better detailed that subject. The addendum states that Whitewater Wind LLC would provide a security bond for the duration of the wind farm project to pay for decommissioning, with the amount of that security bond to be looked at after an initial eight-year period and then reevaluated every five years after for the life of the project.

Even that wording, however, raised eyebrows for residents concerned whether the county could be stuck with the cost of decommissioning the wind turbines – which at this time cost roughly $100,000 to decommission – should the Whitewater Wind LLC, formed by NextEra, go belly-up and a security bond could not be obtained from the dissolved entity.

In the county’s response to the lawsuit, it listed several defenses as to why judgment should be in favor of the county and NextEra in the lawsuit.

Among those defenses are that the plaintiff ’s “claims are barred because there is no privity of contract between Plaintiff ’s and Defendant,” along with the plaintiffs having “no actionable property right.”

It also denies that the decommissioning addendum does not conform with county zoning ordinances and their decision was “arbitrary and capricious.”

The county, in its response, also claims it has legislative immunity and that the lawsuit is not suitable for a declaratory ruling.

The plaintiffs are seeking a declaratory judgment by the Fayette Circuit Court in the case which deems both the Decommissioning Plan and its addendum between the county and NextEra Energy Resources be declared invalid and void, for failing to comply with the county’s zoning ordinance. It also seeks “costs of this action” and other relief.

A response from NextEra Energy Resources, the co-defendant in the civil suit, has yet to be filed with the Fayette County Clerk’s Office.

NextEra and its counsel have until June 22 to file their response to the suit.


URL to article:  https://www.wind-watch.org/news/2016/06/17/local-judge-bows-out-of-wind-farm-battle/