By
Tomasz Janas,
Michal Motylewski,
Agnieszka Skorupinska |
Dentons |
2/22/2016 |
www.jdsupra.com
Today, 19/02/2016, the Law and Justice Party brought to the Sejm (lower chamber of the Parliament) a project of an Act on wind turbines investments.
The breaking points introduced with respect to the wind turbines investments are:
-
New wind turbines may be only located on the basis of a local zoning plan;
-
The minimum distance between the wind turbine and households or buildings of mixed purpose should be equal or higher than ten-times total height of the wind turbine (mast plus blade);
-
Operating wind turbines which do not meet the distance requirement may only be under maintenance works;
-
Operating wind turbines require obtaining a new type of operation permit from the Technical Supervision Authority (UDT) within one year from the entry in force of the Act;
-
Issued building permits will remain in force under the condition that the occupancy permit will be obtained within 3-years from the entry in force of the Act;
-
Where existing local zoning plans allow for location of wind turbines new building permits will not be issued if the minimum distance requirement is not met;
-
Zoning decisions for wind turbines issued before the entry in force of the Act which do not comply with the minimum distance requirement expire, unless a building permit was issued before laps of this 1-year period.
URL to article: https://www.wind-watch.org/news/2016/02/22/new-draft-law-on-wind-turbines-location/