LOCATION/TYPE

NEWS HOME

[ exact phrase in "" • results by date ]

[ Google-powered • results by relevance ]


Archive
RSS

Add NWW headlines to your site (click here)

Get weekly updates

WHAT TO DO
when your community is targeted

RSS

RSS feeds and more

Keep Wind Watch online and independent!

Donate via Stripe

Donate via Paypal

Selected Documents

All Documents

Research Links

Alerts

Press Releases

FAQs

Campaign Material

Photos & Graphics

Videos

Allied Groups

Wind Watch is a registered educational charity, founded in 2005.

News Watch Home

Utility regulators reject requests for new hearing on Badger-Coulee transmission line 

Credit:  By Chris Hubbuch | La Crosse Tribune | June 3, 2015 | lacrossetribune.com ~~

Utility regulators have denied a request to re-consider their approval for a high-voltage power line that will cut through the Coulee Region as it carries electricity to Madison.

Several groups opposed to the $580 million project known as Badger-Coulee petitioned the Public Service Commission for a new hearing on its April decision.

The three-member PSC voted unanimously Wednesday morning to reject requests, standing behind the legality of their approval for the controversial project.

“Our process in the decision making was solid,” said Commissioner Phil Montgomery.

A joint venture of Xcel Energy and American Transmission Co., the 345-kilovolt line will originate at a substation under construction near Briggs Road that is part of CapX2020, another high-voltage transmission project running across Minnesota and western Wisconsin. Crews are at work raising towers along the $211 million portion of that project between Alma and Holmen, with work expected to be completed this summer.

ATC and Xcel say the project will improve system reliability, deliver cheaper power and provide a pipeline for wind energy from Minnesota and Iowa to population centers to the east. Opponents contended the line will allow utilities to profit by trading energy while discouraging more cost-effective local alternatives such as energy efficiency and solar power.

Two grassroots organizations, the Citizens Energy Task Force and Save Our Unique Lands claimed new evidence supported their position that the line is not needed, citing data from the federal Energy Information Administration that shows U.S. electricity sales fell steeply during the recession and have not grown since rebounding in 2010.

In Wisconsin, they pointed out, sales last year were about 1.8 percent below 2005.

“I don’t find that persuasive,” said Commissioner Mike Huebsch of West Salem.

Chairwoman Ellen Nowak said the project would provide a net benefit even at 0.2 percent growth.

A group of 30 Dane County landowners filed a separate rehearing petition Wednesday asking the PSC to reject a 4.6-mile segment near Middleton, noting that route comes within 100 feet of three homes. As an alternative, they ask commissioners to require ATC to bury the line, a more expensive option.

Like SOUL and CETF, the Segment A landowners argue the PSC failed to determine the project’s cost-benefit ratio for electric consumers. The project could end up losing money, they argue. And while state law allows utilities to recoup losses, there are no such protections for customers.

{p dir=”ltr”}CETF spokeswoman Deb Severson said she still believes the case was decided on bad information but that her organization will likely not challenge the decision in court.

{p dir=”ltr”}“I hope we’ve made a good strong difference in our educational efforts,” she said.

The town of Holland has challenged the decision in circuit court, also arguing that the line is not needed and the decision was based “on deficient environmental analysis.”

{p dir=”ltr”}The PSC has until July 24 to respond.

Construction of the new line is not expected to begin until 2016, but ATC said it will begin acquiring easements along the route next month, working from south to north. Altogether, there are 318 residences – including 169 homes – within 300 feet of the approved route, which cuts through 617.5 acres of farmland.

Source:  By Chris Hubbuch | La Crosse Tribune | June 3, 2015 | lacrossetribune.com

This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.

The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.

Wind Watch relies entirely
on User Funding
   Donate via Stripe
(via Stripe)
Donate via Paypal
(via Paypal)

Share:

e-mail X FB LI M TG TS G Share


News Watch Home

Get the Facts
CONTACT DONATE PRIVACY ABOUT SEARCH
© National Wind Watch, Inc.
Use of copyrighted material adheres to Fair Use.
"Wind Watch" is a registered trademark.

 Follow:

Wind Watch on X Wind Watch on Facebook Wind Watch on Linked In

Wind Watch on Mastodon Wind Watch on Truth Social

Wind Watch on Gab Wind Watch on Bluesky