LOCATION/TYPE

NEWS HOME

[ exact phrase in "" • results by date ]

[ Google-powered • results by relevance ]



Archive
RSS

Add NWW headlines to your site (click here)

Get weekly updates

WHAT TO DO
when your community is targeted

RSS

RSS feeds and more

Keep Wind Watch online and independent!

Donate via Stripe

Donate via Paypal

Selected Documents

All Documents

Research Links

Alerts

Press Releases

FAQs

Campaign Material

Photos & Graphics

Videos

Allied Groups

Wind Watch is a registered educational charity, founded in 2005.

News Watch Home

CapX2020 transmission line changed lives, laws 

Credit:  Kirsti Marohn | St. Cloud Times | May 9, 2015 | www.sctimes.com ~~

SOUTH HAVEN – In many ways, Bradley and Linda Lindberg’s life has improved since a high-voltage transmission line project caused them to leave their beloved home and hobby farm near Clearwater.

They’ve relocated to a new place 6 miles to the southwest, in a sprawling farmhouse with a wrap-around front porch and barns for their cattle, goats, horses and chickens. A peaceful spot overlooking rolling pastures and far from major highways, it’s unlikely to be on the route of any new power lines.

But Brad Lindberg still has trouble driving by their old farm, where he and Linda had planned to stay the rest of their lives. And although things have improved, the Lindbergs look back at the past few years as a stressful time they wouldn’t wish on anyone.

“It was a lot of being in limbo, not knowing how it was going to end up,” Linda Lindberg said. “You just felt like you weren’t settled for a long time.”

The Lindbergs are one of the last affected landowners along the route of the transmission line known as CapX2020 with an unresolved legal case. They’re still waiting to find out if the utility companies will pay their legal bills, which they say total six figures.

The two longest sections of CapX2020, part of one of the biggest public infrastructure projects in Minnesota, are now complete. Last week, supporters of the project gathered at a new substation in St. Cloud for a dedication ceremony of the lines that run from Monticello to Fargo and from Hampton to Brookings, South Dakota, about 500 miles. Both lines were energized within the last two months.

Costing more than $1 billion – as much as the new Vikings stadium – the two CapX2020 lines involved a partnership of 11 utility companies, including Xcel Energy and Great River Energy.

More capacity

CapX2020 was born in 2004 when utility leaders began talking about the need for increased reliability and expanding electrical transmission to meet growing demand in Minnesota.

“Here we are, 11 years later, and what we planned actually turned out to be what we needed,” Will Kaul, vice president of transmission at Great River Energy, said last week. “It’s just in time, when the concern about the grid and the security and resilience of the grid is very high, at a time when the resource mix that is coming into play is in transition and new resources are coming online.”

The project also created thousands of jobs during the recession when they were badly needed, Kaul said.

CapX attracted support from some unlikely places, including environmental groups that believed more transmission lines were needed for renewable energy.

“Transmission was truly the glass ceiling for wind development,” said Beth Soholt, executive director of Wind on the Wires, a St. Paul-based nonprofit that works to bring wind energy to market. “There was simply not enough transmission capacity to deliver the thousands of megawatts of new wind power that was envisioned for the Midwest.”

What followed was a lengthy process to get approval from state and local regulators, as well as the necessary agreements from landowners. There were dozens of public meetings around the state before the state Public Utilities Commission approved the project and settled on final routes.

Buy the Farm

The project tested a 1973 Minnesota law designed to protect farmers whose land was taken for major transmission lines. Known as “Buy the Farm,” the law allows landowners to require that the utility company purchase their entire property outright, rather than just buying an easement.

However, the law hadn’t been used much since its passage, and it left a lot of questions that the CapX utilities and landowners along the lines fought over in court.

In total, CapX dealt with about 2,000 landowners on the project, and about 100 of those requested Buy the Farm, said Tim Carlsgaard, Xcel’s spokesman for CapX. About 30 of those were on the Monticello-to-Fargo line, the Lindbergs among them.

Just two cases remain open, and the parties are negotiating settlements, Carlsgaard said.

The total cost of buying right of way for the $640 million Monticello-to-Fargo line was about $60 million, higher than originally anticipated, Carlsgaard said.

Some landowners accused CapX of stalling and objecting to Buy the Farm requests for questionable reasons. Many expressed frustration at the length of time it took to settle their cases.

Igor Lenzner, whose St. Cloud law firm, Rinke Noonan, represented dozens of CapX cases, said his office has only one case that hasn’t settled.

“For some of these people, it’s dragged out for years, and it’s been stressful,” he said. “A lot of it was sitting back and waiting for some of the fights that had to happen.”

About a year ago, CapX stopped fighting many of the Buy the Farm cases and project backers said they would buy the properties if they could come to a reasonable figure, he said.

“At first, nobody knew the limits of the law,” Lenzner said. “They didn’t know the scope of how many of these there would be.”

After a few years, it became clear there weren’t going to be a huge number of Buy the Farm requests, Lenzner said.

“I think part of it is time,” he said. “They were able to see that it wasn’t this giant wave of Buy the Farms that was going to overwhelm the project.”

Cases also settled more quickly after a Minnesota Supreme Court decisions in favor of landowners with contested Buy the Farm requests.

The legal fights over Buy the Farm set a precedent for future projects, said Thom Petersen, government relations director for the Minnesota Farmers Union. He noted that the courts consistently ruled in favor of the landowners.

“It all comes down to there’s a cost for public infrastructure, and farmers understand that, but they want to get paid fairly for their land when it gets taken,” Petersen said. “I think we ended up getting to that point.”

Source:  Kirsti Marohn | St. Cloud Times | May 9, 2015 | www.sctimes.com

This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.

The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.

Wind Watch relies entirely
on User Funding
   Donate via Stripe
(via Stripe)
Donate via Paypal
(via Paypal)

Share:

e-mail X FB LI M TG TS G Share


News Watch Home

Get the Facts
CONTACT DONATE PRIVACY ABOUT SEARCH
© National Wind Watch, Inc.
Use of copyrighted material adheres to Fair Use.
"Wind Watch" is a registered trademark.

 Follow:

Wind Watch on X Wind Watch on Facebook Wind Watch on Linked In

Wind Watch on Mastodon Wind Watch on Truth Social

Wind Watch on Gab Wind Watch on Bluesky