McCarthy Tétrault LLP | Carole J. Piovesan and Eric Pellegrino | January 12, 2015 | www.lexology.com
The approval of industrial wind turbine projects is often met with resistance from the communities in which the projects are to be built. Residents (or businesses) located in close proximity to project sites often challenge the location of a project on the basis that the turbines cause harm to human health or environment.
Dixon v. Director, Ministry of the Environment is an important case, particularly for those tracking renewable energy or large-scale rural land development projects in Ontario. Dixon is an appeal of three decisions of the Environmental Review Tribunal to approve three wind turbine projects in Bruce and Huron Counties in Ontario. Darryl Cruz, Chris Wayland and Eric Pellegrino of McCarthy Tétrault successfully represented the developer of one of the projects, St. Columban Energy Inc.
Background
In 2013 and 2014 the Director of the Ministry of the Environment (the “Director”) authorized the construction and operation of three separate wind turbine generation farms in Huron and Bruce Counties by St. Columban Energy LP (“St. Columban Wind Project”), K2 Wind Ontario Limited Partnership (“K2 Wind Project”) and SP Armow Wind Ontario LP (“Armow Wind Project”) respectively. Each wind project was to be located in close proximity to residents who objected to the construction of the wind farms in their communities.
Approval and Appeal Process
In order to construct and operate a large wind power project in Ontario, a developer must first obtain a Renewable Energy Approval (“REA”) from the Director. Part V.0.1 of the Environmental Protection Act (the “EPA”) establishes a statutory regime for the issuance and review of REAs.
Under s. 142.1 of the EPA, any resident in Ontario may appeal the issuance of a REA to the Environmental Review Tribunal (the “Tribunal”) on the basis that the project, as approved:
Subsection (a) – serious harm to human health – is at issue in this case.
Environmental Review Tribunal
The appellants appealed the REAs issued for the three projects, challenging the Director’s decision on two grounds. First, the appellants argued that the projects would cause serious harm to human health. Second, the appellants challenged the constitutionality of the statutory test itself (particularly subsection (a) above) on the basis that it violated their security of the person according to s. 7 of the Charter.
The Tribunal dismissed all three appeals.
As to the first issue, the Tribunal found that the appellants failed to lead any evidence that the projects would cause “serious” harm to human health, despite it being the appellants’ burden to establish a positive determination in that regard.
As to the second issue, the Tribunal rejected the argument that the REA appeal provisions violated the Charter.
Appeal to the Divisional Court
The appellants appealed the Tribunal’s decisions to the Divisional Court on the basis that the decisions were constitutionally flawed and procedurally unfair. The three appeals were heard concurrently.
Constitutional Question
The appellants’ argued, among other things, that the Tribunal’s decisions were constitutionally flawed for the following reasons:
The Divisional Court dismissed the appellants’ arguments for the reasons that:
Procedural Fairness
The appellants raised a number of issues relating to the Tribunal’s alleged denial of procedural fairness and natural justice, all of which were dismissed by the Court.
Potential Significance
This case engages the sensitive question of safe proximity of wind farms to residents or local businesses. In this case, the Court rejected the anecdotal evidence of the post-turbine witnesses and Health Canada as demonstrating that wind turbine farms, as presently constituted under the regulations, pose a serious harm to human health. In so doing, Dixon indirectly confirms that the distance of 550 meters of turbines from residents/businesses, at a volume of no more than 40 decibels at the lowest specified wind speed, is acceptable.
URL to article: https://www.wind-watch.org/news/2015/01/12/550-meters-proximity-of-wind-turbine-projects-to-residents-confirmed-by-the-divisional-court/