October 22, 2014
Maine

High court supports BEP decision to permit Passadumkeag Mountain wind farm

By Erica Stapleton | WABI TV5 | Tuesday, October 21st, 2014 | wabi.tv

The Maine Supreme Judicial Court has upheld the Board of Environmental Protection’s decision to grant permission for a wind farm on Passadumkeag Mountain in Grand Falls Township.

Last year, the BEP overturned a decision by the Department of Environmental Protection to reject the 14-turbine wind farm.

Passadumkeag Mountain Friends, a non-profit group fighting against the project, appealed the decision to the high court.