Towns eye green power solution
Credit: BRUCE ERSKINE, BUSINESS REPORTER | The Chronicle Herald | December 19, 2013 | thechronicleherald.ca ~~
Translate: FROM English | TO English
Translate: FROM English | TO English
Berwick and Mahone Bay are closer to generating their own green electricity.
The Alternative Resource Energy Authority, a partnership of the two municipalities, registered its proposed 16.1-megawatt, seven-turbine Ellershouse Wind Farm in western Hants County for environmental assessment Thursday.
Environment Minister Randy Delorey will decide on or before Feb. 17 if the project, which would generate enough energy to power 4,500 homes, can be granted conditional environmental assessment approval.
Pending approval, construction of the project southeast of Windsor is anticipated to begin in mid-2014, with operations to begin in 2015.
Don Regan, Berwick’s chief administrative officer and superintendent of the Berwick Electrical Commission, said Thursday he thought the project’s chances of getting conditional environmental approval were “very good” to “excellent.”
Both towns have utilities that will use the wind energy.
Regan said the project will help the utilities meet provincial renewable energy standards while providing lower and less volatile electricity costs to their combined 2,150 customers.
Berwick and Mahone Bay now buy electricity wholesale from Nova Scotia Power.
Regan said the authority, which expects the town of Antigonish to become a partner, plans to initially build four turbines with a 9.2-megawatt generating capability at a cost of about $25 million.
Minas Energy of Hantsport will build the Ellershouse project. Minas Energy is part of Scotia Investments Ltd.
Minas Energy spokeswoman Mary-Frances Lynch said Thursday the project will also require a development agreement with the Municipality of the District of West Hants.
Regan said the project, sited in West Hants because of its wind resource, its proximity to transmission lines and its distance from residential areas, has reasonable support from the municipality’s council.
West Hants Warden Richard Dauphinee could not be reached for comment Thursday.
Copies of the environmental assessment registration information are at Ellershouse Post Office, 382 Ellershouse Rd.; Municipality of the District of West Hants, 76 Morison Dr., Windsor; Ecology Action Centre, 2705 Fern Lane, Halifax; the Nova Scotia Environment Department, 30 Damascus Rd., Suite 115, Bedford Commons; Nova Scotia Environment Department library, 1903 Barrington St., Suite 2085, Halifax, and online at www.gov.ns.ca/nse/ea.
Written comments can be sent to the Environmental Assessment Branch, Nova Scotia Environment Department, P.O. Box 442, Halifax, N.S., B3J 2P8, on or before Jan. 28.
The department can be contacted by phone at 424-3960, by fax at 424-6925 or by e-mail at EA@gov.ns.ca.
All submissions, including personal information, will available for public review at the Nova Scotia Environment Department library, Barrington Place, Suite 2085, 1903 Barrington St.
This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.
Wind Watch relies entirely on User Contributions |
(via Stripe) |
(via Paypal) |
Share: