A 750 tonne All Terrain crane overturned yesterday on a wind farm in Germany as it was moving – partially rigged – between turbine installation areas.
The crane, a new Liebherr LTM 1750-9.1 owned by Cologne based crane specialist Colonia, had already completed its work on two turbines at the wind farm in Düren-Echtz – between Aachen and Cologne – and was moving along one of the wind farm roads to the third turbine, when it went over.
Local police say that a strong gust of wind caught the crane, but this was most likely combined with the uneven ground at the point where it went over. The crane was said to have overturned slowly, which suggests that some of the wheels had left the main part of the road. It was rigged with an extension and jib and had most of its counterweight in place.
The operator was rescued from his cab by the emergency services and was taken to hospital suffering from shock. No one else was hurt in the incident, although the crane which was delivered in July will have sustained some serious damage.
[additional photos at source]
This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.
Wind Watch relies entirely on User Contributions |
(via Stripe) |
(via Paypal) |
Share: