Corsbie Moor wind farm refusal appeal dismissed
Credit: The Southern Reporter | 05 September 2013 | www.thesouthernreporter.co.uk ~~
Translate: FROM English | TO English
Translate: FROM English | TO English
The decision to turn down the appeal over the rejected Corsbie Moor wind farm proposal has been hailed a victory by campaigners.
Scottish Government reporter Trevor Croft announced his decision following a public hearing and several visits to the site between Earlston and Lauder where German energy company, E.on, wanted to erect nine 450-foot high turbines.
The original proposal was refused unanimously by Scottish Borders Council’s planning committee last September.
Mr Croft agreed that the scheme would have had an unacceptable detrimental landscape impact and an unacceptable cumulative impact when taken together with other existing turbine sites.
Professor Jack Ponton, chairman of the Lauderdale Preservation Group set up to campaign against E.on’s proposals, says the reporter’s decision vindicates its opposition to the scheme, as well as that of the local authority, four community councils and individual objectors.
Professor Ponton commented: “On the same day, a different reporter dismissed the appeal for Horn Burn, near Ayton and Eyemouth. The following day yet another appeal was refused, this time the one at Gilston.”
“Given the track record of reporters, this is astonishing. Something like 80 per cent of wind turbine appeals succeed, and around Lauderdale it’s 100 per cent.
“The team from SBC did a really good job at the appeal – I was very impressed. Their performance was very strong and they put together a good case.”
And at the planning committee’s meeting this week, legal adviser Nuala McKinlay said the three appeal results endorsed the decisions the committee “rightly” took and further ratified the crucial work council officers.
“It is gratifying that their work has been recognised,” she added. Councillors also praised the efforts of planning officers, landscape architect, archaeologist, legal team and others for the work taken both on the initial planning reports and the subsequent appeal process.
Earlier this month, councillors also unanimously refused plans for eight turbines at Brunta, near Spottiswoode – although the firm involved, PNE Wind UK, has now indicated it intends to appeal.
But proposals for seven schemes, totalling up to 87 turbines, for sites in or around Lauderdale, are still at various stages in the planning process.
In a statement on its website, E.on said it was disappointed with the outcome of the appeal.
“We will now review our plans to decide on the best way forward for the project,” it said.
This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.