PSC formally dismisses Galloo Island transmission line application
Credit: Galloo Island wind... | By JAEGUN LEE, TIMES STAFF WRITER | THURSDAY, JUNE 6, 2013, watertowndailytimes.com ~~
Translate: FROM English | TO English
Translate: FROM English | TO English
The state Public Service Commission has put the final nail in the coffin of Upstate NY Power Corp.’s Galloo Island Wind Farm transmission line application.
In his order of dismissal, PSC acting Secretary Jeffrey C. Cohen reiterated the fact that Upstate NY had been “afforded a great deal of time to move forward substantively on this application” yet has not made any progress for well over a year.
In January 2009, Upstate NY asked the state to approve construction of a 50.6-mile electric transmission line that would connect the company’s proposed 246-megawatt wind farm on Galloo Island, town of Hounsfield, to the Fitzpatrick-Edic Substation in the town of Mexico, Oswego County.
But the ruling process for the transmission line had been delayed several times at Upstate NY Power’s request.
“The applicant has not reported any progress or movement on this project since at least late October 2011, when the New York Power Authority (NYPA) denied the applicant’s proposal for a power purchase agreement and terminated its Great Lakes Offshore Windfarm (GLOW) initiative,” Mr. Cohen said.
Unable to find a customer, the developer floated the idea of selling power to Fort Drum, but the Army did not react publicly to that proposal.
“The potentially affected landowners assert that, due to this pending proceeding, they cannot develop their agricultural business properties until they know if, and in what manner, the proposed project will impact their properties,” Mr. Cohen said,
Both the PSC staff and administrative law Judge Kevin J. Casutto had used the same reasoning in their recommendations to dismiss Upstate NY’s application.
“The applicant filed no response to staff’s counter-motion to dismiss and has filed no interlocutory appeal following issuance of the ruling referring this case to the commission,” Mr. Cohen said.
The application was dismissed without prejudice, meaning that Upstate NY would be allowed to file another application in the future.
This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.
Wind Watch relies entirely on User Contributions |
(via Stripe) |
(via Paypal) |
Share: