Developer asked to mitigate environmental issues
Credit: Lassen County Times | www.lassennews.com 21 June 2012 ~~
Translate: FROM English | TO English
Translate: FROM English | TO English
The Bureau of Land Management (BLM) has yet to approve Invenergy’s Horse Lake Wind Farm project, and has asked the developer to mitigate several environmental concerns.
Ken Collum, field manager for the BLM’s Eagle Lake office, said the agency sent Invenergy a letter in May requesting a development alternative that is completely outside of Sage-Grouse habitat.
Moving the project to the north and the east would eliminate some habitat areas.
The Sage-Grouse may be listed as threatened or endangered species in 2015, so BLM asked Invenergy to develop an alternative.
Collum said the BLM also has asked the developer to do additional studies on the impact the project will have on golden and bald eagles “to determine the use and extent of their range within the project area.”
He said that study is expected to take another season or a year to complete.
“The notice of intent to begin the environmental impact statement is prepared,” Collum said, “but it will not be issued or signed until these additional studies are complete.”
This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.
Wind Watch relies entirely on User Funding |
(via Paypal) |
(via Stripe) |
Share: