NextEra suspends South Dakota wind farm without power deal
Credit: By Andrew Herndon, Bloomberg, www.bloomberg.com 19 October 2011 ~~
Translate: FROM English | TO English
Translate: FROM English | TO English
NextEra Energy Inc. (NEE), the largest U.S. wind-energy producer, suspended the permitting process for a wind farm it’s developing in South Dakota until a customer for the power is found.
The company told the U.S. Energy Department to cancel an environmental review of its proposed 150-megawatt Hyde County Wind Energy Center, the agency said today in a statement. The review was initiated when NextEra requested permission to connect its plant to the grid.
NextEra “decided not to move forward” with the review “until we have greater clarity on several issues including securing a customer for the output,” Steve Stengel, a spokesman for the Juno Beach, Florida-based company, said today in an e- mail.
The energy producer has purchased the land and completed other “environmental field work” for the project, he said. NextEra may resume work on the wind farm later and would require a new environmental review, according to the statement.
This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.
Wind Watch relies entirely on User Contributions |
(via Stripe) |
(via Paypal) |
Share: