March 8, 2011
Wisconsin

Glenmore Town Board postpones wind turbine decision

Written by Tony Walter, Green Bay Press-Gazette, www.greenbaypressgazette.com 8 March 2011

GLENMORE – The Glenmore Town Board voted Monday to wait 60 days before voting on a permit request to have seven wind turbines built in the town.

In an emotion-filled meeting that at one point had Town Chairman Don Kittell call in police officers when residents began chanting and shouting, the board reversed an earlier vote to approve the permits.

Mark Dick of Cenergy, a subsidiary of Pennsylvania-based CG Power Solutions that is seeking to erect the turbines, said the board’s delay on a decision was based on emotion and opinion, not law.

“You’re asking the Town Board to violate law,” Dick told the more than 100 residents who crowded into the Glenmore Community Center. “You might as well as ask them to outlaw smoking.”

The board voted quickly at the meeting’s outset to approve the permits, with Kittell and Supervisor Kriss Schmidt supporting it and Supervisor Ron Nowak opposing it. Kittell argued that the board was simply following the law that required it to honor a conditional use permit that went into effect before the town changed its wind turbine ordinance last year.

But residents reacted angrily, chanting, “No permits,” then “change your vote,” prompting Kittell to call for police support.

“The people are trying to get out of hand,” Kittell said on his cell phone. One Wisconsin State Patrol officer and two Brown County Sheriff’s Department officers showed up 15 minutes later.


URL to article:  https://www.wind-watch.org/news/2011/03/08/glenmore-town-board-postpones-wind-turbine-decision/