LOCATION/TYPE

NEWS HOME

[ exact phrase in "" • results by date ]

[ Google-powered • results by relevance ]


Archive
RSS

Add NWW headlines to your site (click here)

Get weekly updates

WHAT TO DO
when your community is targeted

RSS

RSS feeds and more

Keep Wind Watch online and independent!

Donate via Paypal

Donate via Stripe

Selected Documents

All Documents

Research Links

Alerts

Press Releases

FAQs

Campaign Material

Photos & Graphics

Videos

Allied Groups

Wind Watch is a registered educational charity, founded in 2005.

News Watch Home

PUC rejects CMP’s proposal for Lewiston upgrade 

Credit:  By Scott Taylor, Lewiston Sun Journal, bangordailynews.com 1 March 2011 ~~

LEWISTON, Maine  – The Public Utilities Commission on Tuesday rejected the Lewiston portion of Central Maine Power Co.’s proposed $1.4 billion power line upgrade.

The Lewiston loop of the Maine Power Reliability Project called for $108 million in upgrades to the city’s electrical delivery system. More than $71 million was to be used to build a new substation on Larrabee Road.

PUC commissioners ruled that CMP’s plan didn’t thoroughly enough consider alternatives to the Lewiston upgrades, including lower voltage options to provide electricity without transmission lines. Options could have included generating electricity locally – solar, wind or river power – or reducing consumer electrical demand through conservation.

“CMP has not met its burden of proof in this case,” PUC Commission Chairman Jack Cashman said in a written statement. “The utility has not shown to my satisfaction through comprehensive testing or analysis that construction of the Lewiston Loop project is the most cost-effective means of addressing power reliability needs in the Lewiston area.”

Phil Nadeau, deputy city administrator, said he was concerned that the denial could hurt the utility’s ability to deliver electricity to Maine’s second-largest city.

“There is certainly necessity for the Lewiston loop,” Nadeau said. “We could be looking at a downtown casino and an entire riverfront development. All of that needs electricity, and that’s the one thing a city of our size should never have to worry about. In my mind, the state should bend over backwards to make sure Lewiston has what it needs to do the economic development and the job creation they want us to do.”

CMP spokesman John Carroll said he was waiting to get a written copy of the commission’s findings before discussing the company’s response.

“One thing they have talked about is needing more analysis,” Carroll said. “That would be the most logical place for us to start.”

CMP’s Maine Power Reliability Project calls for upgrading a swath of power lines beginning in Eliot in southern Maine and passing through central Maine to Orrington, where the lines would connect to lines from Canada. Along the way, they pass through Litchfield, Monmouth, Leeds, Greene, Lewiston and a corner of Auburn at the Durham line.

In some places, lines would be rebuilt or replaced. In other places, lines would be added, including 115-kilovolt and 345-kilovolt lines. The 345-kilovolt poles, not common in Maine, are wider than traditional power-line towers and can be 20 to 25 feet taller than the lower-voltage poles.

Commissioners approved the bulk of the statewide program in June 2010, delaying a decision on the improvements where they passed through Lewiston.

The City Council approved a tax incentive in July 2009 to convince the utility to move some of its proposed lines around some residents’ homes. CMP agreed. Those changes added an estimated $3.5 million to the utility’s costs.

CMP was expected to pay an additional $1.2 million to Lewiston in new property taxes for the new substation and new power lines. The tax incentive agreement would have returned $358,723 of those new taxes to the utility each year.

Source:  By Scott Taylor, Lewiston Sun Journal, bangordailynews.com 1 March 2011

This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.

The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.

Wind Watch relies entirely
on User Funding
   Donate via Paypal
(via Paypal)
Donate via Stripe
(via Stripe)

Share:

e-mail X FB LI M TG TS G Share


News Watch Home

Get the Facts
CONTACT DONATE PRIVACY ABOUT SEARCH
© National Wind Watch, Inc.
Use of copyrighted material adheres to Fair Use.
"Wind Watch" is a registered trademark.

 Follow:

Wind Watch on X Wind Watch on Facebook Wind Watch on Linked In

Wind Watch on Mastodon Wind Watch on Truth Social

Wind Watch on Gab Wind Watch on Bluesky