NEW ZEALAND: State-owned energy company Mighty River Power has won draft approval for a wind farm at Turitea on New Zealand’s North Island, but with fewer turbines than the original proposal.
The company applied for 105 turbines however the draft consent only allows for 61. According to reports the original aim was to build a wind farm in the 300MW range.
The company said the decision would adversely impact the economics of the project.
Mighty River general manager for development Mark Trigg said: “We now need to work through the detail of the decision and consider next steps. The next milestone is the board of inquiry’s final decision.”
The project was called in by the minister for the environment Nick Smith in 2008 and referred to an independent board of inquiry.
New Zealand has three onshore projects coming forward in 2011. The biggest of these is Mighty River Power’s Kaiwera Downs, Southland, which should generate 360MW.
This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.
Wind Watch relies entirely on User Contributions |
(via Stripe) |
(via Paypal) |
Share: