LOCATION/TYPE

NEWS HOME

[ exact phrase in "" • results by date ]

[ Google-powered • results by relevance ]


Archive
RSS

Add NWW headlines to your site (click here)

Get weekly updates

WHAT TO DO
when your community is targeted

RSS

RSS feeds and more

Keep Wind Watch online and independent!

Donate via Stripe

Donate via Paypal

Selected Documents

All Documents

Research Links

Alerts

Press Releases

FAQs

Campaign Material

Photos & Graphics

Videos

Allied Groups

Wind Watch is a registered educational charity, founded in 2005.

News Watch Home

Fire Island wind farm has yet to generate contracts 

Credit:  By ELIZABETH BLUEMINK, Anchorage Daily News, www.adn.com 8 September 2010 ~~

With nearly $44 million in federal money available to help build a Fire Island wind farm set to expire this year, electric companies are still weighing whether to buy the wind power – a vital step before the $162 million project can happen.

Chugach Electric Association, the Railbelt’s largest power company, is the giant at the negotiating table. But two other major power utilities are in talks, too.

Anchorage-based Cook Inlet Region Inc., which wants to develop the wind farm, said it hopes to sign power-purchase agreements with at least one electric utility. CIRI needs to have deals to sell the farm’s power to win the $43.8 million in federal grant available as well as obtain the rest of the money needed to build the project.

Getting the utilities on board hasn’t been easy, however. The Chugach board of directors weighed in recently. The board voted 6-1 on a motion reminding its staff that the clock is ticking on the grant and telling them to negotiate with CIRI to see if a fair deal can be reached.

CIRI says its project would supply nearly 4 percent of the Railbelt’s electricity, bring a relatively low-cost, clean-energy project to the region and help reduce the regional electrical grid’s reliance on turbines fueled by Cook Inlet natural gas, which is in tight supply.

The project is not a simple sell to the electric companies for several reasons.

For one, the power generated from Fire Island turbines, which could start producing as early as 2012, would cost several pennies per kilowatt hour more than gas-fueled electricity, according to CIRI’s calculations. But CIRI says its rates will be flat over time, while gas rates are expected to rise above the wind rates within a few years.

Chugach Electric staff are worried about its cost to retool equipment so that wind power can enter Chugach’s aging power grid, something they’re now studying. Further, Chugach staff are studying how to protect the reliability of its power supply when winds dramatically fluctuate.

CIRI has a cost estimate for integrating wind into the grid, but Chugach staff have not accepted it and are doing their own. A “better estimate” should be available within weeks, according to Chugach spokesman Phil Steyer.

Anchorage city officials are also noncommittal about Fire Island. “I’m just not sure yet whether they have hit the price point where it’s economical for ML&P to purchase power,” Anchorage Mayor Dan Sullivan said about the city-owned Municipal Light & Power utility.

“This is a big decision for us, my board, the Assembly and the Regulatory Commission of Alaska,” said ML&P general manager Jim Posey.

“My board has to consider it, the Assembly has to consider it and the mayor signs (off) on it. I’m moving as fast as I can,” he said.

The Native firm said more than $6 million has been spent on the project so far and it plans to spend another $3 million this year. CIRI won’t seek additional financing to build until it signs up electric companies and gets regulatory approval.

A CULTURAL ISSUE?CIRI says it has presented price terms to Chugach, ML&P and Fairbanks-based Golden Valley Electric Association and is involved in discussions with all three.

But ML&P board member Charles Wohlforth, a supporter of the Fire Island project, said he is worried that the Anchorage utilities – including his own – will dicker over the project until the federal funding disappears and that, without this subsidy, the project could be in serious trouble.

“There hasn’t been a can-do attitude to get it done. If the mayor wants this project to happen, he can make it happen. He can get the people in the room to get (a) contract. If he doesn’t want it to happen, it’s very easy to stall and make objections,” Wohlforth said.

Sullivan said Wednesday he’s relying on the ML&P staff to evaluate the project’s viability.

“The key will be the cost of the kilowatt hour to the residents of Anchorage,” he said.

Posey said, “It’s a matter of how much data is available and how comfortable we are with the data.”

A BIG CHANGE?

Chugach staff declined to discuss how their negotiations with CIRI are going, citing a confidentiality agreement they signed with CIRI.

The chairman of the utility’s board, Jim Nordlund, said he thinks the Chugach staff is working diligently.

But, “The timing is critical, to be candid,” he said. The federal grant appears to be a one-shot deal, he said.

Wohlforth said he thinks the CIRI wind proposal poses some cultural challenges for the Railbelt utilities.

“They have never dealt with an independent power producer,” he said.

In Anchorage, “They have been comfortable with the way they’ve always done it,” negotiating long-term contracts with the major Cook Inlet natural gas producers, he said.

If they sign a deal with CIRI, the utilities – not CIRI – will determine what to charge their customers for the wind power. The Regulatory Commission of Alaska will have to approve those rates.

Posey wants the project costs to be brought down because he fears it might be too expensive for ML&P customers in Anchorage, who generally pay less for electricity than Chugach customers in the city.

But CIRI says the project is about as cheap as it can get right now. The company points out that the project’s installed cost per kilowatt hour would be cheaper than at least four wind projects in Washington state and Oregon, for example. The company also predicts the project will add “only a few pennies per day” to Railbelt utility customer bills.

However, both those cost estimates are contingent on CIRI receiving the $43.8 million federal grant.

Source:  By ELIZABETH BLUEMINK, Anchorage Daily News, www.adn.com 8 September 2010

This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.

The copyright of this article resides with the author or publisher indicated. As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Send requests to excerpt, general inquiries, and comments via e-mail.

Wind Watch relies entirely
on User Funding
   Donate via Stripe
(via Stripe)
Donate via Paypal
(via Paypal)

Share:

e-mail X FB LI M TG TS G Share


News Watch Home

Get the Facts
CONTACT DONATE PRIVACY ABOUT SEARCH
© National Wind Watch, Inc.
Use of copyrighted material adheres to Fair Use.
"Wind Watch" is a registered trademark.

 Follow:

Wind Watch on X Wind Watch on Facebook Wind Watch on Linked In

Wind Watch on Mastodon Wind Watch on Truth Social

Wind Watch on Gab Wind Watch on Bluesky