July 4, 2007
Idaho

Utilities propose settlement with wind developers

Idaho’s three large regulated electric utilities have proposed a settlement with wind developers that they say could resolve cost issues that have slowed development of small wind projects in Idaho.

Idaho Power had asked the Public Utilities Commission to place a moratorium on rapidly increasing wind development projects within its territory while the company studied how much it would cost the utility to accept wind-generated power and to provide for backup generation when wind output is less than projected.

The commission denied the request, and it reduced the size of wind projects that could qualify for the commission-posted rates that utilities must pay generators of small renewable power projects. It lowered the size of wind projects that qualify for the posted rates from 10 megawatts to 100 kilowatts.

Having completed their studies, Idaho Power, Avista Corp. and PacifiCorp are recommending that the published rate for wind-generated power be discounted to allow for wind intermittency and that the size limit of projects that can qualify for the rate be brought back to 10 megawatts.

Statesman staff

Idaho Statesman

4 July 2007


URL to article:  https://www.wind-watch.org/news/2007/07/04/utilities-propose-settlement-with-wind-developers/