February 28, 2007
Idaho

Idaho commission approves two wind power agreements

The Idaho Public Utilities Commission has approved two wind power purchase agreements for the Idaho Power Co., a Boise, Idaho-based electric utility.

The first is a 20-year sales agreement with Houston-based Telocaset Wind Power Producers LLC for 100 MW of wind energy. According to the commission, Telocaset’s wind farm is scheduled to be complete by March 2008.

The second agreement the commission approved is between Idaho Power Co. and Idaho Winds LLC, which plans to build The Alkali Wind Farm six miles northwest of Glenns Ferry.

The project includes 12 turbines that will be operating by Dec. 31. Even though the maximum output of the project is 18 MW, it will not generate more than 10 MW on average on a monthly basis, the commission says. Energy delivered in excess of that amount may be accepted, but Idaho Power will not be obligated to pay for it under the Public Utility Regulatory Policies Act.

By NAW Staff
North American Windpower

nawindpower.com

28 February 2007


URL to article:  https://www.wind-watch.org/news/2007/02/28/idaho-commission-approves-two-wind-power-agreements/