Matter of Brander v Town of Warren Town Bd.
Author: | Environment, Filings, Law, New York, Noise, Siting
Translate: FROM English | TO English
Translate: FROM English | TO English
This Article 78 petition seeks to annul and vacate actions taken and determinations made by the respondent town boards, alleging a violation of, inter alia, the State Environmental Quality Review Act (SEQRA) and the Open Meetings Law. The proposed project is for the construction a 68 turbine wind farm in the [*2]subject towns in Herkimer County which, when fully operational, will generate 136 megawatts of electric power from the wind which will be introduced into the New York State Electric Grid.
The petitioners allege that the Warren Town Board, as the SEQRA lead agency, and the respondents Jordanville Wind, LLC (hereinafter “Jordanville”) and Community Energy, Inc. (hereinafter “CEI”) engaged in scoping for the Draft Environmental Impact Statement (DEIS) for the project in a way that prevented the petitioners and other members of the public from participation and that they thus committed a fatal procedural SEQRA error…
This material is the work of the author(s) indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this material resides with the author(s). As part of its noncommercial educational effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information, National Wind Watch endeavors to observe “fair use” as provided for in section 107 of U.S. Copyright Law and similar “fair dealing” provisions of the copyright laws of other nations. Queries e-mail.
Wind Watch relies entirely on User Contributions |
(via Stripe) |
(via Paypal) |
Share:
Tags: Wind power, Wind energy