Xcel Energy
Download video (52-MB MP4) [1]
- 100 Vestas V100 2-MW turbines
- Nearly 25,000 acres (101 kmĀ²)
- 22 miles of access roads
- Substation transformer: 262,000 pounds
- Substation increases voltage for transmission lines
- 17.1-mile 115-kV overhead transmission line from collection substation to interconnect substation
- More than 150 miles of underground cable in 50 miles of trench
- Tower base (platform) excavation depth: 9 feet
- 360 cubic yards of concrete, 28 tons of reinforcing steel
- Tower base (bottom third): 96,000 pounds, 128 anchor bolts
- Nacelle: 163,650 pounds
- Hub height: 262 feet
- Turbine blade: length 161 feet, weight 17,000 pounds
- Total height: 426 feet
- Blade diameter: 328 feet
- Blade sweep area: 1.94 acres