Estimate: €900,000+ to dismantle and dispose of one turbine
Montpellier, January 29, 2008 Sirs, Following the consultation that you asked for, here is the estimate that we propose for the dismantling and demolition of wind turbines in the commune of Saint Etienne de Lugdares. The dismantling and demolition require the presence on site of: One 700-tonne crane and two 50-tonne cranes. A Copex CVM 500 metal press and shredder. A team of five people for 30 working days for unbolting, blow-torching, and shredding the metal parts. Class II disposal . . . Complete article »