LINCOLN, Maine — Maine regulators are moving toward denial of the Bowers Mountain Wind Power Project in eastern Maine.
Meeting in Lincoln, the Land Use Regulation Commission on Wednesday voted to instruct its staff attorneys to write a denial order for the project, which would straddle Penobscot and Washington counties.
Champlain Wind LLC, a subsidiary for First Wind, proposes the 27-turbine Bowers wind farm. The land use commission is to take up the proposal again in December and decide whether to deny a permit.
The 69-megawatt project would be constructed on Bowers Mountain, and an unnamed ridge in Carroll Plantation and Dill Hill in Kossuth Township.
[rest of article available at source]
Source: Associated Press,
www.therepublic.com
20 October 2011
This article is the work of the source indicated. Any opinions expressed in it are not necessarily those of National Wind Watch.
The copyright of this article is owned by the author or publisher indicated. Its availability here constitutes a "fair use" as provided for in section 107 of the U.S. Copyright Law as well as in similar "fair dealing" exceptions of the copyright laws of other nations, as part of National Wind Watch's noncommercial effort to present the environmental, social, scientific, and economic issues of large-scale wind power development to a global audience seeking such information. For more information, click here. Send requests to excerpt and takedown inquiries to DMCA/wind-watch.org. Send general inquiries and comments to query/wind-watch.org.

[ Short URL: http://wind-watch.org/news/?p=14556 ]
Translate: FROM English | TO English
« Later Post • News Watch Home • Earlier Post »