Take a break
While Palmerston North City Council has walked a tightrope between commercial imperatives and local loyalties over the past four years, Mighty River Power’s stance has always been clear – they want to generate electricity and make money. Civic reporter Katie Chapman found out the State Owned Enterprise’s views on the issues.
We need electricity. Wind can create electricity. Mighty River Power (MRP) can harvest wind.
Usually, a resource consent application is heard by the local authority, which then makes a ruling, granting or denying the application. Often, granted applications also have conditions imposed. This can then be appealed to the Environment Court, and this is a common occurrence for wind farm applications. A call-in would fast-track this process by skipping the local authority stage. Instead, Environment Minister Trevor Mallard can send it straight to the Environment Court or a board of inquiry. Interested parties would still be able to make submissions, but the decision reached could only be appealed on a point of law to the High Court. The minister may call in any application he deems to be of ‘‘national significance’’. 136 potential turbines sites, of National significance is defined by a variety of factors, including whether the matter: has aroused widespread public concern or interest regarding its actual or likely effect on the environment involves significant use of natural and physical resources affects any structure, feature, place, or area of national significance affects more than one region or district affects or is relevant to New Zealand’s international obligations to the global environment involves technology, processes or methods which are new to New Zealand and which may affect the environment results in or contributes to significant or irreversible changes to the environment is significant in terms of the Treaty of Waitangi. about 10km south-east of Palmerston North, mostly stretching along a 14km ridge in the northern Tararua Ranges, with turbines in and around Turitea Reserve. Driving down Fitzherbert Avenue toward Massey University, the turbines would be visible along the skyline. The turbines would range in output from 2-3.5 megawatts. We’ve heard from the city council and Mighty River Power, but what about the residents? And finally: We look at the cumulative effect on the Manawatu skyline.
Simple? That’s the way it is, and MRP makes no secret about it.
The company’s website proclaims: ‘‘Energy is integral to modern society. Our primary objective is the ongoing production and provision of renewable energy to New Zealand, now and for generations to come.’’
The key word, group strategist Neil Williams says, is ‘‘renewable’’.
The Government has committed to having 90 percent renewable energy by 2025.
As a State Owned Enterprise MRP has a key role to play in reaching that goal, and wind is an important resource, he says.
‘‘Wind power currently only accounts for about 1.5 percent of the electrical energy generated in New Zealand. We believe there is considerable potential to increase that proportion.’’
And, as far as world wind resources go, the Tararua Ranges are one of the best, unique in New Zealand and internationally.
‘‘The northern Tararua Ranges have long been identified as an area with an abundant wind resource . . . more consistent, and of high enough speed, to make it a wind resource that is . . . unique. . .’’
Frequently cited figures put the site in the top 5 percent in the world for wind power.
But, while the public generally accepts the country needs more power, it is the scale of the proposed Turitea Wind Farm that has some people balking.
Is it really necessary to have 131 turbines, some within 700 metres of houses?
Original documents from 2006, when the reserve status was changed to allow electricity generation, suggest 63 in the reserve and an ‘‘undisclosed number’’ on private land.
The application is now for 66 in the reserve, and 70 outside, totalling 136 turbine sites. Of those, only 131 will be built.
On top of that, there are pylons, cables and substations to make sure the energy harvested can be sent to the national grid.
Even city councillors who voted for the reserve change concede they never imagined that many turbines.
But, MRP was always upfront, Mr Williams says. ‘‘It was never intended that the project would be entirely contained within the reserve, and we have always been entirely open about that.’’
And, as for the distance from houses – ‘‘all the turbine locations proposed comply with the Palmerston North district plans and relevant national standards and guidelines.’’
Projects development manager Stuart McDonnell explained at the time why the details were kept hidden until just before the resource consent application was lodged.
The information could not have been provided earlier because it didn’t exist at that stage. Major investigations into the shape a wind farm might take only began after the land use change was confirmed and the conditions set.
‘‘Until we got that, certainly we couldn’t get down to the detail.’’
Other concerns have focused on the potential environmental effect of a wind farm on the reserve, especially since it is home to the city’s main water supply.
Those concerns are justified, Mr Williams says, but he is confident any potential impacts can be mitigated.
‘‘The nature of wind projects, like all electricity generation projects, is that they do carry some environmental impact.’’
The council’s decision from 2006 puts in place some protections for the water reserve, specifying where turbines could be located and insisting on a $20 million public liability insurance policy for the water supply.
That relationship with the city council has also been fraught, as people questioned whether it compromised the independence of the parties.
Mr Williams says it doesn’t, and he is happy with the relationship.
‘‘The agreement acknowledges that council has certain public or statutory functions as a territorial authority outside of the agreement. The agreement provides that council’s obligations under the agreement cannot fetter council undertaking its public or statutory functions.
‘‘We have a constructive relationship with the Palmerston North City Council and have had since being selected as their development partner in late 2005.’’
Yet, despite this ‘‘constructive relationship’’, MRP has applied for a ministerial call-in on the project, a step that would fasttrack the project, by-passing the council’s part in the resource consent process.
At a public meeting about the call-in, councillors unanimously voted to oppose it, and many condemned MRP for making the request.
Breaking of trust and ‘‘bullying tactics’’ were among the comments around the table.
But Mr Williams says it’s all about efficiency, not bullying.
‘‘When it comes to significant wind projects, decisions made at a local level are almost inevitably appealed to the Environment Court; asking the minister to refer the project direct to the Environment Court or a board of inquiry offers the most efficient way for the matter to be heard in a transparent manner and still provide opportunity for local input.’’ And, after all, that means getting more electricity, sooner.
Manawatu Standard
6 October 2008
Tags: Wind power, Wind energy
Some possibly related stories:
The copyright of this article is owned by the author or publisher indicated. Its availability here constitutes a "fair use" as provided for in section 107 of the U.S. Copyright Law as well as in similar "fair dealing" exceptions of the copyright laws of other nations, as part of National Wind Watch's effort to advance understanding of the environmental, social, scientific, and economic issues of large-scale wind power development. For more information, click here.